Los Angeles County · SB 1117 · 42 days until Jan 1, 2027
Burbank ADU Impact Fees: Before and After SB 1117
From January 1, 2027, SB 1117 charges impact fees on a homeowner's first two ADUs only for the square footage above 750. Here is what that does to Burbank's verified impact-fee lines — permit in 2026 vs permit in 2027.
Verified rows only; every line links to its official source. Last verified 14 Nov 2026. How we price →
Impact fees by ADU size
| ADU size | Permit in 2026 | Permit in 2027 | Difference |
|---|---|---|---|
| 750 sq ft | $0 | $0 | exempt either way |
| 800 sq ft | $7,078 | $7,078* | $0 |
| 1,000 sq ft | $7,078 | $7,078* | $0 |
| 1,200 sq ft | $7,078 | $7,078* | $0 |
* Burbank has flat impact fees with no published conversion to the excess-area rule. Rather than guess, the 2027 column carries them at their 2026 amount — so the real 2027 bill could be lower and the real saving larger than shown.
Dwelling-base flat fees are prorated (ADU ÷ primary) and converted assuming a 1,600 sq ft primary dwelling — an assumption, not a verified figure. The calculator lets you enter your actual primary size for an exact figure.
Line by line at 1,000 sq ft
1,000 sq ft puts 250 sq ft above the 750 line — the 2027 column charges only that excess.
| Impact fee | 2026 | 2027 | Source |
|---|---|---|---|
| Development Impact Fees (Transportation + Community Facilities, pro-rata) | $7,078 | not published | official doc ↗verified 7 Oct 2026 |
What SB 1117 does not change
School developer fees, building permit and plan-check fees, and water/sewer connection or capacity charges stay the same. SB 1117 covers a homeowner's first two ADUs. This is a fee comparison, not advice to wait: delay, construction-price movement and financing have costs of their own.
Common questions
How much does SB 1117 save on ADU fees in Burbank?
Computed savings at 800 sq ft are $0, but $7,078 in flat impact fees has no published conversion yet, so the real change could be larger. Computed savings at 1,000 sq ft are $0, but $7,078 in flat impact fees has no published conversion yet, so the real change could be larger. Only impact fees change; school fees, permit fees and utility connection or capacity charges stay the same.
Should I wait until January 2027 to pull an ADU permit in Burbank?
This page compares fees only. In Burbank we found no verified impact-fee difference at the sizes shown. Waiting also has costs — schedule changes, construction-price movement, financing — and SB 1117 applies to a homeowner's first two ADUs. Weigh both before deciding.
Does SB 1117 change anything for ADUs of 750 sq ft or less?
No. ADUs of 750 sq ft or less already owe $0 in impact fees under Gov. Code §66311.5. SB 1117 changes what happens above 750 sq ft: impact fees apply only to the square footage over 750 instead of the whole unit.
Background: SB 1117 in plain English · Wait or permit now? · The 750 sq ft cliff