Orange County · SB 1117 · 42 days until Jan 1, 2027
Orange (city) ADU Impact Fees: Before and After SB 1117
From January 1, 2027, SB 1117 charges impact fees on a homeowner's first two ADUs only for the square footage above 750. Here is what that does to Orange (city)'s verified impact-fee lines — permit in 2026 vs permit in 2027.
Verified rows only; every line links to its official source. Last verified 15 Oct 2026. How we price →
Impact fees by ADU size
| ADU size | Permit in 2026 | Permit in 2027 | Difference |
|---|---|---|---|
| 750 sq ft | $0 | $0 | exempt either way |
| 800 sq ft | $548 | $548* | $0 |
| 1,000 sq ft | $548 | $548* | $0 |
| 1,200 sq ft | $548 | $548* | $0 |
* Orange (city) has flat impact fees with no published conversion to the excess-area rule. Rather than guess, the 2027 column carries them at their 2026 amount — so the real 2027 bill could be lower and the real saving larger than shown.
Dwelling-base flat fees are prorated (ADU ÷ primary) and converted assuming a 1,600 sq ft primary dwelling — an assumption, not a verified figure. The calculator lets you enter your actual primary size for an exact figure.
Line by line at 1,000 sq ft
1,000 sq ft puts 250 sq ft above the 750 line — the 2027 column charges only that excess.
| Impact fee | 2026 | 2027 | Source |
|---|---|---|---|
| Fire Protection Facilities DIF — ADUs on R-1 lots exempt ($0) | $0 | not published | official doc ↗verified 15 Oct 2026 |
| Police Facility Development DIF — ADUs on R-1 lots exempt ($0) | $0 | not published | official doc ↗verified 15 Oct 2026 |
| Library Facilities DIF (proportionate, 800 sq ft ADU worked example) | $548 | not published | official doc ↗verified 15 Oct 2026 |
What SB 1117 does not change
School developer fees, building permit and plan-check fees, and water/sewer connection or capacity charges stay the same. SB 1117 covers a homeowner's first two ADUs. This is a fee comparison, not advice to wait: delay, construction-price movement and financing have costs of their own.
Common questions
How much does SB 1117 save on ADU fees in Orange (city)?
Computed savings at 800 sq ft are $0, but $548 in flat impact fees has no published conversion yet, so the real change could be larger. Computed savings at 1,000 sq ft are $0, but $548 in flat impact fees has no published conversion yet, so the real change could be larger. Only impact fees change; school fees, permit fees and utility connection or capacity charges stay the same.
Should I wait until January 2027 to pull an ADU permit in Orange (city)?
This page compares fees only. In Orange (city) we found no verified impact-fee difference at the sizes shown. Waiting also has costs — schedule changes, construction-price movement, financing — and SB 1117 applies to a homeowner's first two ADUs. Weigh both before deciding.
Does SB 1117 change anything for ADUs of 750 sq ft or less?
No. ADUs of 750 sq ft or less already owe $0 in impact fees under Gov. Code §66311.5. SB 1117 changes what happens above 750 sq ft: impact fees apply only to the square footage over 750 instead of the whole unit.