Published: 7 Nov 2026 · Last verified: 10 Nov 2026 · Next review: Dec 2026 City totals marked * are preliminary (matrix-based); full six-phase posts for each city are linked below. Changes logged in Corrections.
Thirty miles apart, three completely different theories of what an ADU should cost the city — and the homeowner. Riverside barely charges for the permit. Fontana’s impact fee schedule starts at $20,563 per single-family unit. San Bernardino wrote the clearest 750 sq ft cliff in California code. This is the Inland Empire’s ADU math, side by side.
The table
| 800 sq ft detached ADU · 2026 | Riverside | Fontana | San Bernardino |
|---|---|---|---|
| Total | $309,000 | ~$305,000* | ~$300,000* |
| Per sq ft | $386 | ~$381* | ~$375* |
| School fee | $4,136 | $4,304* | $4,304 |
| Impact / DIF | Low* | ~$10,967* | Proportional* |
| Building permit | $1,006 | $3,195 (flat) | Verify* |
| Sewer | Verify* | ~$1,023* | Proportional* |
| Free plans | 800 sq ft | 738 sq ft (3 designs) | None found |
| 750 cliff | Yes | Yes | §19.04.030 (clearest) |
* Preliminary — see each city’s full post for the verified ledger.
Three philosophies
Riverside: the permit minimalist. The $1,006 building permit is the lowest in the entire series — and the city pairs it with free pre-approved plans at exactly 800 sq ft, the benchmark size this series uses. No scaling down to dodge a cliff, no valuation surprises. Riverside’s theory: make the paperwork cheap and the drawings free, and the ADUs will come. At $309,000 total, it’s the series-low candidate among fully published cities.
Fontana: the impact-fee maximalist. The development impact fee schedule opens at $20,563 per single-family dwelling unit — then scales down proportionally for the ADU (roughly $10,967 on our 800 sq ft example). But Fontana also issues three pre-approved designs including a 738 sq ft plan — twelve feet under the cliff, where the DIF line reads $0. The city’s left hand charges; its right hand shows you the door. School fees at the $5.38 state ceiling ($4,304) complete the high-soft-cost picture, offset by a flat $3,195 permit with no valuation math.
San Bernardino: the plain-language cliff. Municipal Code §19.04.030 states the 750 sq ft rule in the clearest ordinance language we’ve found in California — no fee-schedule footnotes, no planner interpretation required. The DIF ($17,330.78 per single-family unit, scaled proportionally) and a rare area-based sewer formula round out a code-first approach: everything in the ordinance, nothing hidden in a spreadsheet.
What the verified rows say
The table above mixes verified lines with preliminary ones — the asterisks mark the preliminary figures. Here is what the fee data actually verifies for each city, line by line.
Riverside: three verified lines. The $1,006 permit is the verified New SFD R-3 line for 800 sq ft: $0.53 per sq ft for plan check plus $0.53 per sq ft for the permit, a $39 issuance fee, a 10% General Plan maintenance fee, and a 4% technology fee — $1,005.72, rounded to $1,006 (City of Riverside Building & Safety Fee Schedule, June 2025). The school fee is Riverside USD at $5.17 per sq ft — one tier below the $5.38 ceiling — or $4,136 on 800 sq ft. A roof-based storm drain fee of $214 is also verified. Note the school figure: the table above showed $4,304 for Riverside; the verified RUSD rate makes it $4,136.
Fontana: seven verified permit lines. The $3,195 “flat permit” is the building permit ($1,892) plus plan check ($1,303) for the 501–1,200 sq ft tier. Five smaller verified lines sit on top of it: permit issuance $71, disabled access review $117, state energy review $117, training fee $4.80, and computer fee $0.50 — $310.30 in all, for a $3,505.30 permit stack (City of Fontana Listing of City Fees, Jan 1, 2026). The development impact fee is $0 for an ADU under 750 sq ft (verified). Fontana’s school fee is the $5.38 ceiling ($4,304), but the district’s board vote is unconfirmed — it stays preliminary.
San Bernardino: one verified line, one code formula. The school fee is San Bernardino City USD at $5.38 per sq ft, verified — $4,304 on 800 sq ft. Everything else runs on Municipal Code §19.04.030(2)(P)(7): subsection (a) sets the impact fee as the ADU’s square footage divided by the primary dwelling’s, times the $17,330.78-per-unit standard (2022 base, adjusted every July 15 by the ENR index); subsection (b) exempts conversion ADUs from new utility connections while requiring new detached ADUs to connect separately and pay proportionally. No verified dollar figure exists yet for the permit or the sewer line — the table marks them “Verify”.
What the region tells you
The Inland Empire is not “cheap” — it’s bimodal. Riverside’s $1,006 permit and Fontana’s $20,563 DIF schedule coexist in the same metro. The regional average means nothing; the parcel-specific fee sheet means everything.
Free plans cluster here. Two of the three cities offer free pre-approved ADU designs, and both sized them at or under the cliff (Riverside’s 800 is the benchmark exception that proves the program’s confidence). Inland Empire planning departments are competing on paperwork, not just fees.
School fees are nearly the constant. San Bernardino and Fontana both sit at the $5.38 state ceiling — $4,304 on 800 sq ft, set by the school districts, untouched by any city policy. Riverside is the exception: Riverside USD charges $5.17, or $4,136 — $168 below the other two. In the Inland Empire, the school fee is still the floor everything else is built on; in Riverside, that floor sits $168 lower.
The bottom line
Pick Riverside for the cheapest permit in the series, Fontana if you can build at 738 sq ft and erase a five-figure DIF line, San Bernardino for the most readable code in California. Same region, same 800 sq ft box — three different answers to what it should cost. Read each city’s full ledger before you pick yours.