Beverly Hills ADU Cost 2026: $305,000 Floor — $0 Water, $0 Wastewater, and a $1,416 Covenant

Edit page

In this series

Every build below uses the same six-phase ledger, so you can compare any two directly.

New construction

Geography

Compare any two builds side by side →

Published: 7 Nov 2026 · Last verified: 7 Nov 2026 · Next review: Feb 2027 Cost figures are re-checked against permit records quarterly. Changes are logged in Corrections.

Beverly Hills is the most expensive city in this series by reputation, and the cheapest by fee schedule. Water capacity $0. Wastewater capacity $0. Planning fee for a building-permit-only ADU $0. The FY 2025–26 master fee schedule prices all three at zero — and there is no impact-fee line for an ADU anywhere in it. What the city does charge is paperwork: a $1,416 covenant recordation fee, a $447 certificate of occupancy, and three small percentage-of-valuation fees that together come to about $649. Our six-phase total lands at $305,000, or $381 per square foot — but it is a floor. The school district fee is not yet verified, so it is not in the total at all.

The valuation assumption does real work here. Three fees are percentages of construction valuation — General Plan Maintenance at 0.187%, the Building Standards Commission fee (SB 1473) at 0.004%, and the Contractor’s Business Tax Registration at 0.2125% — and the city does not publish a valuation for our example. We use $161,120, the assumed valuation from the Torrance post, and label it wherever it appears. On that valuation the three fees come to about $301, about $6 and about $342. Construction phases 2–6 are carried from the Los Angeles County baseline; Beverly Hills does not publish phase-level construction costs.

The short answer

800 sq ft detached ADU · Beverly Hills · 2026Amount
Total build cost (floor — see gaps)$305,000
Cost per square foot$381
Largest single lineSystems + interior, $147,000
Building permit + plan check~$2,643 (valuation assumed)
Impact feesNone found
School district feeNot verified (gap)
Water / sewer capacity$0
Pre-approved ADU plansNone found

The full line-item breakdown

Six phases. The same six used on every build in this series.

PhaseCostShare
Soft costs (design, permits, fees)$17,0006%
Site work + foundation$38,00012%
Framing + structure$48,00016%
Building envelope$42,00014%
Systems + interior$147,00048%
Landscaping & hardscape$13,0004%
Total$305,000$381 / sq ft

The fee autopsy

Every fee line we found, with exactly what it is and where it came from.

Fee lineAmountSource / status
Design & engineering$14,000Series baseline, carried — no pre-approved ADU plan program found in city materials (absence not officially confirmed)
Water capacity charge and water supply fee$0FY 2025–26 master fee schedule
Wastewater capacity fee$0FY 2025–26 master fee schedule
Planning fee for a building-permit-only ADU$0FY 2025–26 master fee schedule
Permit Issuance Fee$92FY 2025–26 master fee schedule
State SB 1186 fee (AB 1379)$4FY 2025–26 master fee schedule
Vandalism Remediation Fee$35FY 2025–26 master fee schedule
Certificate of Occupancy (ADU)$447FY 2025–26 master fee schedule
ADU covenant processing (recordation)$1,416FY 2025–26 master fee schedule
General Plan Maintenance / Long Range Planning Fee~$3010.187% of valuation — valuation $161,120 assumed (carried from the Torrance post)
Building Standards Commission fee (SB 1473)~$60.004% of valuation — same assumed valuation
Contractor’s Business Tax Registration (per project)~$3420.2125% of valuation — same assumed valuation
Permit + plan-check lines, subtotal~$2,643$1,994 flat + ~$649 valuation-based
School district feenot verifiedNo verified school-fee row on file for Beverly Hills — not in the total
Impact feesnone foundNo impact-fee line for an ADU in the FY 2025–26 master fee schedule

Soft costs in the breakdown table are rounded to $17,000 (exact $16,643); the total is rounded to the nearest $1,000.

The city’s fee lines are also listed on the Beverly Hills fee page, with verification status and source links.

The $0 city

Three zeroes in a row is the story of this post. The water capacity charge and water supply fee: $0. The wastewater capacity fee: $0. The planning fee for a building-permit-only ADU: $0. All three are printed as $0 in the FY 2025–26 master fee schedule — not waived for ADUs, not missing from the schedule, priced at zero.

The water and wastewater zeroes are partly state law doing its work. Gov. Code §66311.5 bars a city from requiring a new or separate water or sewer connection for an ADU on an existing single-family lot, so an ADU that shares the existing service has nothing to pay on those lines in any city. Beverly Hills is unusual in printing the $0 rather than leaving the line out. The planning $0 is different: it is a city choice. A building-permit-only ADU — one that needs no discretionary review — pays no planning fee at all.

The $1,416 covenant

If the city gives with one hand, it takes with the other, and the taking is a single line: ADU covenant processing, $1,416. The covenant is the recorded agreement that ties the ADU to the lot — the document that says this unit is an ADU, with the use restrictions that follow. Beverly Hills charges $1,416 to process and record it, more than three times the $447 certificate of occupancy and more than fifteen times the $92 permit issuance fee. It is the largest single flat fee in the post, and it is pure paperwork: no inspection, no capacity, no square footage. Every ADU in Beverly Hills pays it.

The rest of the permit column is small change by comparison. Permit issuance $92, the state SB 1186 disability-access fee $4, the vandalism remediation fee $35, the certificate of occupancy $447 — $578 before the covenant, $1,994 after it. The three valuation-based fees add about $649 on the assumed valuation. The whole permit column is about $2,643, which is less than the school fee alone in most cities in this series.

Valuation does the work

Three fees are percentages of construction valuation, and the valuation is the one number in this post we do not have from the city. We use $161,120 — the assumed valuation from the Torrance post (800 sq ft × $201.40) — and every fee computed from it is marked with a tilde. On that valuation: General Plan Maintenance at 0.187% is about $301; the Building Standards Commission fee (SB 1473) at 0.004% is about $6; the Contractor’s Business Tax Registration at 0.2125% is about $342.

If the real valuation is higher, these three fees rise with it — but they are small percentages, so the movement is small. A $50,000 higher valuation adds about $94 to the General Plan fee, $2 to the SB 1473 fee and $106 to the contractor tax: about $200 on a $305,000 total. The valuation assumption is not the risk in this post. The missing school fee is: at the $5.38 state maximum it would add $4,304.

Beverly Hills vs. Los Angeles County

Beverly HillsLA County baseline
Total$305,000 (floor)$320,000
Per sq ft$381$400
Building permit + plan check~$2,643 (valuation assumed)carried
Impact feesNone foundcarried
School feeNot verified$4,304
Water / sewer capacity$0carried
Pre-approved ADU plansNone foundnone

The $15,000 gap to the baseline is almost entirely the missing school fee. Add $4,304 for the school fee at the state maximum and the gap closes to about $11,000 — still under the baseline, because there is no impact fee to pay. The real story is the composition: the most expensive city in the series by reputation, with no impact fee, no water or wastewater capacity charge, no planning fee, and a $1,416 covenant as its biggest single charge.

A note on SB 1117

Signed September 2026, effective January 2027: for a homeowner’s first two ADUs, impact fees may apply only to square footage above 750, calculated marginally. Beverly Hills has no verified impact-fee lines, so SB 1117 changes nothing we can compute here — there is nothing to reduce. See the full comparison at Beverly Hills: 2026 vs 2027, line by line. School fees, permit fees and water/sewer charges are outside SB 1117’s impact-fee definition and do not change.

Disclaimer

Model estimate, not a quote. Fees change; the assumptions above are the city’s to confirm — the construction valuation ($161,120 assumed), the school district fee (not yet verified), and the pre-approved plan program’s existence are all marked where they appear. Always verify current fees with the City of Beverly Hills before budgeting.

Frequently asked questions

How much does an ADU cost in Beverly Hills in 2026?

About $305,000 for an 800 sq ft detached, single-story, new-construction unit with mid-grade finishes in Beverly Hills — roughly $381 per square foot. That total is a floor: the school district fee is not yet verified, so it is not in the total. The three percentage-of-valuation fees are computed on an assumed $161,120 construction valuation, carried from the Torrance post and labelled where they appear. Construction phases 2–6 are carried from the Los Angeles County baseline; Beverly Hills does not publish phase-level construction costs.

Does Beverly Hills charge impact fees on ADUs?

We found no impact-fee lines for an ADU in the city's FY 2025–26 master fee schedule — no DIF, no parks, no traffic, no per-square-foot impact charge. What it does charge is a $1,416 covenant recordation fee, a $447 certificate of occupancy, and three small percentage-of-valuation fees. ADUs of 750 sq ft or less owe $0 in impact fees under state law (Gov. Code §66311.5) in any case.

Why is the water capacity charge $0 in Beverly Hills?

The city's FY 2025–26 master fee schedule lists the water capacity charge and water supply fee at $0, and the wastewater capacity fee at $0. State law (Gov. Code §66311.5) already bars a city from requiring a new or separate water or sewer connection for an ADU on an existing single-family lot, so the example shares the existing service and pays $0 on both lines.

New line-item breakdowns and quote-check tips by email

Occasional emails when a new cost breakdown goes up. No contractor leads. Unsubscribe anytime.


Edit page
Share this post:

Previous Post
Inland Empire ADU Fees Compared: Riverside vs Fontana vs San Bernardino
Next Post
Napa ADU Cost 2026: $325,000 — A $10,033 Sewer Capacity Charge Tops the Ledger

Keep reading

Calculate your exact fees →