Published: 27 Nov 2026 · Last verified: 27 Nov 2026 · Next review: Jan 2027 Cost figures are re-checked against permit records quarterly. Changes are logged in Corrections.
Search the City of Alhambra’s master fee schedule for the word “impact” and you get zero hits. Not a fee that skips ADUs, not a fee schedule that buries it — no development impact fee at all. In a series where DIFs run from Salinas’s full exemption to Ontario’s $37,595-per-dwelling heavyweight, Alhambra’s zero is its own kind of statement, and its fee profile is shaped by what fills the gap: a $2,000 New Construction Tax on every ADU, a valuation-based permit the city prices in official example estimates, and the steepest water-meter step-up in the series — $448 without a new meter, $7,222 with one.
Our six-phase total lands at $316,000, or $395 per square foot — just under the LA County baseline. Two items carry asterisks rather than certainties: the school fee ($3,032) is what the city’s March 2026 fee schedule tells applicants, but the district’s own current board-adopted rate could not be confirmed; and the water line assumes no new meter ($448) rather than the $7,222 alternative. The regional sewer layer — LA County Sanitation District fees, paid directly to the district — could not be pinned to an ADU-specific figure and is excluded. Construction phases 2–6 are carried from the Los Angeles County baseline; Alhambra does not publish phase-level construction costs.
The short answer
| 800 sq ft detached ADU · Alhambra · 2026 | Amount |
|---|---|
| Total build cost (see assumptions) | $316,000 |
| Cost per square foot | $395 |
| Largest single line | Systems + interior, $147,000 |
| Building permit + plan check | ~$8,021* (850 sf official proxy) |
| School fee (Alhambra Unified SD) | $3,032* (possibly stale) |
| New Construction Tax | $2,000 |
| Development impact fee | $0 (not levied) |
| Utilities improvement (no new water meter) | $448 |
| Pre-approved plans | none free (SGVCOG vendor plans are paid) |
The full line-item breakdown
Six phases. The same six used on every build in this series.
| Phase | Cost | Share |
|---|---|---|
| Soft costs (design, permits, fees) | $27,501 | 9% |
| Site work + foundation | $38,000 | 12% |
| Framing + structure | $48,000 | 15% |
| Building envelope | $42,000 | 13% |
| Systems + interior | $147,000 | 47% |
| Landscaping & hardscape | $13,000 | 4% |
| Total | $316,000 | $395 / sq ft |
The fee autopsy
Every fee line we found, with exactly what it is and where it came from.
| Fee line | Amount | Source / status |
|---|---|---|
| Design & engineering | $14,000 | Series baseline, carried — no free city plans (SGVCOG vendor-owned designs are purchased, not free) |
| Building permit + plan check | ~$8,021* | City’s official estimates (Dec 2025 ADU handout) for an 850 sq ft ADU: permit $4,276.84 + plan check $3,744.37. No 800 sq ft figure published — 850 is the closest proxy. (1200 sf: $5,331.81 + $4,668.00) |
| Fixed per-ADU add-ons | $2,483.69 + % fees | Handout lists: Fire plan check $293.46, Public Works initial plan check $120.25, Planning plan check $120, Utilities plan check $69, issuance $73.98 — plus New Construction Tax $2,000, 0.5% General Plan fee on valuation, 2% plan maintenance fee on permit fees, SMIP, technology fees. Handout totals $11,677.00 for 850 sq ft (excludes separate MEP permits) |
| New Construction Tax | $2,000 | $2,000 per new residential unit — AMC §5.06.030, applies to every ADU |
| Development impact fee | $0 | Not levied. Master Fee Schedule (effective 02-23-26): full-text search for “Impact” = zero hits. No DIF in the ADU handout or ADU FAQ either |
| School fee (AUSD) | $3,032* | $3.79/sf × 800 (City Community Development Fee Schedule, updated March 2026). Stale risk: $3.79 matches the SAB’s 2022 Level 1 cap exactly; the district’s own current board-adopted rate could not be located. Paid directly to AUSD, not the city |
| Utilities improvement fee | $448* | $448 if no new water meter / $7,222 with new water meter (ADU FAQ). Assumes sharing existing service — the $6,774 difference is the steepest meter step-up in the series |
| Regional sewer (LACSD) | not counted | City requires LACSD approval and direct payment of district fees (ADU FAQ; AMC §23.22.040(J)). ADU-specific LACSD fee amount not found — verify with city and district |
Zero hits: the city with no DIF
Alhambra’s Master Fee Schedule, effective February 23, 2026, is a long document — and it contains no impact fee entries. Full-text search: zero. The ADU informational handout (December 2025) and the ADU FAQ list fees by the dozen, and none of them is a development impact fee. That makes Alhambra the series’ cleanest negative: most cities’ fee schedules at least contain a DIF the ADU might be exempt from; Alhambra simply doesn’t levy one. The closest equivalent is the New Construction Tax of $2,000 per new residential unit (AMC §5.06.030), which applies to every ADU at every size — it is a per-unit tax, not a proportional impact fee, and our 800 sq ft example pays exactly $2,000. Because no DIF exists, there is no city-level 750 sq ft cliff to write about; the state baseline (no impact fees under 750 sq ft, proportional at 750+) is the only applicable rule.
The $6,774 water-meter decision
City-side, Alhambra’s utilities line is a cliff of its own. The ADU FAQ puts the Utilities Improvement Fees at $448 if no new water meter versus $7,222 with one — a $6,774 difference hanging on a single design decision. For an 800 sq ft detached ADU sharing the main dwelling’s sewer line (allowed where the applicant shows sufficient capacity and slope, per AMC §23.22.040(J)), the $448 figure is the reasonable assumption, and it’s what the breakdown carries. The regional layer sits on top: the city directs applicants to the LA County Sanitation District for approval and fees paid directly to the district. We searched the LACSD connection-fee documents for an ADU-specific figure and could not confirm one — that line stays out of the total and on the verify list.
$3,032: the school fee with a staleness warning
The $3.79/sq ft figure is what the City of Alhambra’s Community Development Fee Schedule (updated March 2026) tells applicants — $3,032 on 800 sq ft, paid directly to Alhambra Unified, not to the city. The asterisk is deliberate: $3.79 exactly matches the State Allocation Board’s 2022 Level 1 cap, which suggests the city’s table was never updated when the SAB raised caps to $5.17 (2024) and $5.38 (2026). Multiple searches for an AUSD board resolution or developer-fee justification study surfaced only other districts’ documents. So $3,032 is the city’s number, not the district’s verified current rate — and if the district has caught up to a later cap, the true figure is higher. Separately, Alhambra runs its own stricter threshold: school-district clearance is required for all new-construction ADUs regardless of size, and for ADU conversions of 500 sq ft or more — stricter than the state’s 750 sq ft impact-fee threshold.
The 850 sq ft proxy: the permit, estimated by the city itself
Alhambra does not price permits flat; it is valuation-based. But the city does something most cities in this series don’t — it publishes official example estimates. The December 2025 ADU handout gives a Building Permit Fee of $4,276.84 plus a Building Plan Check Fee of $3,744.37 for an 850 sq ft ADU, and $5,331.81 + $4,668.00 for 1,200 sq ft. No 800 sq ft figure exists, so the 850 is the closest official proxy: $8,021.21. The handout’s full 850 sq ft total — $11,677.00 — folds in the fixed add-ons (Fire, Public Works, Planning, Utilities plan checks, issuance), the $2,000 New Construction Tax, the percentage fees, SMIP, and technology fees, before separate mechanical, electrical, and plumbing permits. For comparison, that combined permit-plus-plan-check figure is the highest in the series — higher than Burbank’s $3,692 — though Alhambra pairs it with a $0 DIF, which no other city does.
Alhambra vs. Los Angeles County
| Alhambra | LA County baseline | |
|---|---|---|
| Total | $316,000 | $320,000 |
| Per sq ft | $395 | $400 |
| Building permit + plan check | ~$8,021* (850 sf proxy, series high) | carried |
| DIF | $0 (not levied — series cleanest) | carried |
| New Construction Tax | $2,000 | — |
| School fee | $3,032* (possibly stale) | $4,304 |
| Water / sewer (city-side) | $448* (no new meter) | carried |
| Pre-approved ADU plans | none free (SGVCOG vendor plans paid) | none |
The arithmetic of the profile is unusual: the highest permit-plus-plan-check in the series, offset by the only $0 DIF in the series. The $4,000 gap below the baseline comes from that offset plus the below-baseline school figure. The honest risks run the other way: a school fee that may be stale, an LACSD sewer fee that couldn’t be pinned down, and a $7,222 alternative if a new water meter goes in.
A note on SB 1117
Signed September 2026, effective January 2027: for a homeowner’s first two ADUs, impact fees may apply only to square footage above 750, calculated marginally. Alhambra has no DIF for the cliff to apply to — the smallest SB 1117 story in the series, because there is nothing to recalculate. The $2,000 New Construction Tax applies to every ADU regardless of size and is not an impact-fee line. School fees are outside SB 1117’s impact-fee definition and stay at $3,032 pending verification of the district’s current rate. We found no mention of SB 1117 in city materials; the January 2027 quarterly review will confirm the zero-DIF position holds.
Disclaimer
Model estimate, not a quote. Fees change; the assumptions above are the city’s to confirm — the permit uses the city’s 850 sq ft estimate as a proxy (no 800 sq ft figure published), the school fee is the city’s published figure pending confirmation of the district’s current board-adopted rate, the utilities fee assumes no new water meter ($448; $7,222 with one), and the LA County Sanitation District’s ADU-specific sewer fee could not be confirmed. Always verify current fees with the City of Alhambra Community Development Department before budgeting.
*Permit figure uses the city’s official 850 sq ft estimate as the closest proxy; school fee is the city’s published rate pending district confirmation.