Published: 16 Oct 2026 · Last verified: 9 Oct 2026 · Next review: Jan 2027 Cost figures are re-checked against permit records quarterly. Changes are logged in Corrections.
Every city in this series has a 750 sq ft cliff — except the ones that deleted the cliff entirely. Salinas is the first: $0 in development and traffic impact fees on ADUs, at any size. Not reduced, not pro-rated, not deferred to 2027. Zero, by written city policy, published on the city’s official ADU page.
That single policy decision rearranges the entire fee picture. There is no 749-vs-800 optimization to run, no pro-rata math against the primary dwelling, no SB 1117 countdown that matters — the law arriving January 2027 changes nothing in Salinas, because there was never a cliff to remove. Our 800 sq ft benchmark lands at about $316,000, or $395 per square foot, and the money sits in different lines than anywhere else we have published.
The short answer
| 800 sq ft detached ADU · Salinas · 2026 | Amount |
|---|---|
| Total build cost (see assumptions) | ~$316,000 |
| Cost per square foot | ~$395 |
| Largest single line | Systems + interior, $147,000 |
| Building permit + plan check | ~$6,226 (valuation-based) |
| DIF — development + traffic | $0 (city policy) |
| School district fee (SUHSD) | $4,136 |
| Sewer capacity | $0 (ADU exempt by state law)* |
| Water connection | Not found |
| Free pre-approved plans | 4 designs |
| 750 sq ft cliff | None — no DIF on ADUs |
The full line-item breakdown
Six phases. The same six used on every build in this series.
| Phase | Cost | Share |
|---|---|---|
| Soft costs (design, permits, fees) | ~$28,000 | 9% |
| Site work + foundation | $38,000 | 12% |
| Framing + structure | $48,000 | 15% |
| Building envelope | $42,000 | 13% |
| Systems + interior | $147,000 | 47% |
| Landscaping & hardscape | $13,000 | 4% |
| Total | ~$316,000 | ~$395 / sq ft |
The city’s fee lines are also listed on the Salinas fee page, with verification status and source links.
The fee autopsy
Every fee line we found, with exactly what it is and where it came from.
| Fee line | Amount | Source / status |
|---|---|---|
| Design & engineering | $14,000 | Series baseline, carried — free city plans reduce but don’t eliminate site-specific costs |
| Building permit (valuation) | $2,052 | $1,793 + 37 × $7 — FY 2026/27 fee schedule, $100,001–$500,000 tier |
| Combination permit | $3,078 | 150% of BPF (mechanical/electrical/plumbing included) — same schedule |
| Plan check | $1,847 | 90% of BPF — same schedule |
| General Plan maintenance | $1,004 | $7.35 per $1,000 valuation — Planning fee schedule |
| Technology surcharge | ~$295 | 5% — same schedule |
| Valuation basis | $136,640* | 800 × $170.80 (R-3 Type VB) — our assumption, varies by construction type |
| DIF — development + traffic | $0 | “City of Salinas does not charge development or traffic impact fees for ADU’s” — official ADU page |
| School fee (SUHSD) | $4,136 | $5.17 × 800 — Res 25-98 (Level II applicability unconfirmed) |
| Sewer (M1W capacity) | $0* | $6,093.55/unit exists but state law bars ADU capacity charges — exempt |
| Water (Cal Water) | Not found | No ADU-specific connection fee found |
The valuation trap
Salinas’s permit is valuation-based, and valuation is where the honest uncertainty lives. Our $6,226 example uses the Building Valuation Data table’s R-3 Type VB rate ($170.80/sq ft → $136,640 valuation). Change the construction type and the valuation — and every fee derived from it — moves. A heavier build (Type III) raises the permit; the city, not this post, sets your valuation. Budget the permit as a range, not a number.
The city’s own pre-approved plans hint at the workaround: two of the four designs (749 and 746 sq ft) sit just under 750. The cliff is meaningless for DIF in Salinas — but the permit tiers and the school-fee math still reward smaller footprints, and the plan drawers knew it.
Against the series baseline
| Salinas | LA County baseline | |
|---|---|---|
| Total | ~$316,000 | $320,000 |
| Per sq ft | ~$395 | $400 |
| Building permit + plan check | ~$6,226 (valuation) | carried |
| DIF | $0 (waived) | carried |
| School fee | $4,136 ($5.17) | $4,304 |
| Sewer capacity charge | $0* (exempt) | carried |
| Free pre-approved plans | 4 designs | none |
| 750 sq ft cliff | None | — |
Salinas lands $4,000 under the baseline with a completely different composition: the $0 DIF saves up to $10,000 against Anaheim-style cities, then hands about $6,200 back on the valuation-based permit. It is the clearest demonstration in the series that the cliff is a policy choice — and that deleting it does not make ADUs free, it just moves the money to lines the city still controls.
A note on SB 1117
Signed September 2026, effective January 2027: marginal impact fees above 750 sq ft. See the full comparison at Salinas: 2026 vs 2027, line by line. In Salinas, the marginal rate applies to a $0 base — nothing changes. School fees ($4,136) are outside SB 1117 and unchanged.
Disclaimer
Model estimate, not a quote. Fees change; the assumptions above are the city’s to confirm — the valuation basis, the school district’s current collection rate, and water connection fees are all marked where they appear. Always verify current fees with the City of Salinas before budgeting.