Westminster passed a new fee schedule that took effect September 1, 2025 — and then, as far as the public web can tell, never showed anyone what is in it. The Application Forms and Fees page announces the new schedule; the actual PDF with the numbers cannot be verified online. That is the honesty-forward story of this post: we publish what is confirmed from official sources, and we label everything else “verify with city” instead of estimating.
What is confirmed is genuinely interesting. The park development impact fee runs a proportional calculation against the primary dwelling — and then caps the result at $4,000 flat, the only cap structure in the series. The sewer district publishes a rare ADU-specific capacity rate: $1,002 per 1,000 square feet, or $801.60 for our 800 sq ft example. And the city’s six pre-approved plans include a Plan 1 netting 748 square feet — two square feet under the cliff, which does not look accidental.
Our six-phase total lands at $306,802*, or $384 per square foot — with the asterisk doing heavy lifting. It is a floor: the building permit and the school fee could not be verified, so both are excluded. The old permit structure was valuation-based (plan check at 1.55x and inspection at 1.42x of UAC Table 3-A), which in other cities produces some of the highest permit lines in the series — so this floor may understate the true total by a meaningful margin. Construction phases 2–6 are carried from the Los Angeles County baseline; Westminster does not publish phase-level construction costs.
The short answer
| 800 sq ft detached ADU · Westminster · 2026 | Amount |
|---|---|
| Total build cost (see assumptions) | $306,802* (floor, not a total) |
| Cost per square foot | $384* |
| Largest single line | Systems + interior, $147,000 |
| Building permit | not counted (verify with city — new fee schedule unverifiable) |
| School fee (Westminster School District etc.) | not counted (verify with city — no current published rate) |
| Park DIF — proportional, capped | $4,000 (800 sf behind 1,600 sf house) |
| Sewer capacity (Midway City Sanitary District) | $801.60 |
| Water connection / capacity charge | not counted (verify with city) |
| Pre-approved plans | 6, free (WHA designs) |
The full line-item breakdown
Six phases. The same six used on every build in this series.
| Phase | Cost | Share |
|---|---|---|
| Soft costs (design, permits, fees) | $18,802 | 6% |
| Site work + foundation | $38,000 | 12% |
| Framing + structure | $48,000 | 16% |
| Building envelope | $42,000 | 14% |
| Systems + interior | $147,000 | 48% |
| Landscaping & hardscape | $13,000 | 4% |
| Total | $306,802* | $384 / sq ft* |
The fee autopsy
Every fee line we found, with exactly what it is and where it came from.
| Fee line | Amount | Source / status |
|---|---|---|
| Design & engineering | $14,000 | Series baseline, carried (6 pre-approved WHA plans available free — the alternative, not the assumption) |
| Building permit | not counted | New fee schedule effective 2025-09-01 announced but not verifiable online. Old published structure (PL-102): plan check $50 or 1.55x UAC Table 3-A (whichever higher), construction inspection $45 or 1.42x UAC Table 3-A + $65 issuance. No 800 sq ft figure computable — verify with city |
| Park DIF — ADU 750 SF or larger | $4,000 (cap) | $17,179/single-family dwelling (PL-202, current after annual 7/1 adjustments), prorated to primary dwelling size, capped at $4,000 (e.g., 800 sf behind 1,600 sf = 50% × $17,179 = $8,589.50 → $4,000 cap). ADUs under 750 SF fully exempt (WMC §3.62, Housing Element App. C) |
| Transportation impact fee | not counted | 2023 Housing Element Table 4 shows $0 for a 750 sf ADU; ordinance (§3.58) has no ADU-specific exemption clause — 750+ SF ADU application unconfirmed. Verify with city |
| School developer fee | not counted | Current rate not found on any official district source. Old published figures (WSD $2.62/sf on PL-102; $2.31/sf in 2023 Housing Element) are stale and not used. Parcel sits in 3–4 districts (WSD/GGUSD/Ocean View + HBUHSD) — verify with city and district |
| Sewer capacity — Midway City Sanitary District | $801.60 | ADU-specific: $1,002 per 1,000 sq ft (District Wastewater Capacity Fee Table A, “Accessory Dwelling Unit 84 gpd”), 0.8 × $1,002 |
| Water connection / capacity charge | not counted | City is its own water utility; no ADU-specific water connection fee published. State law limits forcing new connections on ADUs (§66324) — verify with city |
A new fee schedule nobody can read
Councils adopt new fee schedules routinely; what is not routine is a schedule the public cannot see. Westminster’s community development page announces that a new schedule took effect September 1, 2025, but the published document’s contents are not verifiable online — so the valuation bands, the permit tiers, everything the new schedule changed is a blank to us. The old published structure is worth knowing anyway: it was valuation-based with aggressive multipliers — plan check at 1.55x and construction inspection at 1.42x of UAC Table 3-A, plus a $65 issuance fee. That is a heavier structure than most cities in this series, and whatever the new schedule says, it matters. This is the item to settle first with the Building Division — the permit line is the largest known-unknown in the soft costs.
The $4,000 cap: the cliff with a ceiling
Every city in this series treats the 750 sq ft cliff differently — exemptions, proportional charges, flat fees. Westminster’s version is proportional-with-a-ceiling, and it is the only one like it. Under 750 square feet, the park DIF is fully exempt (confirmed in the Housing Element). At 750 and above, the ADU pays proportionally to the primary dwelling — an 800 sq ft ADU behind a 1,600 sq ft house would compute to $8,589.50 — but the city’s PL-202 guide caps the proportional result at $4,000 flat. In practice, almost every realistic ADU-to-house ratio hits the cap: even behind a 3,200 sq ft house, the calculation lands at $4,294.75 and gets capped. The cap turns the cliff into a plateau — cross 750 and you owe $4,000, full stop, regardless of the primary dwelling’s size. Note the base figure: $17,179 per dwelling (adjusted annually each July 1), not the $13,760 in the ordinance text — use the current number.
$801.60: the ADU-specific sewer rate
Sewer capacity fees in this series usually come in per-EDU or per-dwelling-unit form, with the ADU application left ambiguous. The Midway City Sanitary District — which handles Westminster’s wastewater — is one of the rare exceptions: its Wastewater Capacity Fee Table A has an explicit “Accessory Dwelling Unit” line at $1,002 per 1,000 square feet (84 gpd). For 800 sq ft: $801.60. No ambiguity about EDUs, no guessing at fixture counts. The city-side water story is the opposite — Westminster runs its own water utility, but no ADU-specific water connection fee could be found in any official source, so that line stays “verify with city.”
Six free plans, one deliberate 748
The city’s Pre-Approved ADU Construction Plans Program offers six WHA designs, free through an application packet with a liability waiver. Plan 1 grosses 781 square feet — and nets 748, two square feet under the 750 sq ft cliff. Plans 2A through 6 step up from there (791 to 1,198 net). Whether or not the 748 was deliberate, it functions as one: pick Plan 1 and the park DIF is fully exempt under the sub-750 rule, the SB 1117 marginal math never triggers, and the fee story simplifies to sewer plus whatever the school districts charge. Design and engineering stays at the $14,000 series baseline in our numbers — the free plans are the alternative path, not the assumption.
Westminster vs. Los Angeles County
| Westminster | LA County baseline | |
|---|---|---|
| Total | $306,802* (floor) | $320,000 |
| Per sq ft | $384* | $400 |
| Building permit + plan check | unverifiable (new schedule 2025-09-01) | carried |
| Park DIF | $4,000 cap (pro-rata) | carried |
| School fee | not found (current rate) | $4,304 |
| Sewer capacity charge | $801.60 (ADU-specific) | carried |
| Water connection | not found | carried |
| Pre-approved ADU plans | 6, free (Plan 1 nets 748 sf) | none |
The gap to the baseline is almost entirely the missing lines: an unverifiable permit and a missing school fee make this the least complete total in the series, even as the confirmed lines — the $4,000 park cap, the $801.60 sewer rate — are among the most precisely documented. Treat $306,802 as the floor it is: the old valuation-based permit structure (1.55x/1.42x multipliers) suggests the real total has room to climb once the new schedule is readable.
A note on SB 1117
Signed September 2026, effective January 2027: for a homeowner’s first two ADUs, impact fees may apply only to square footage above 750, calculated marginally. Westminster’s $4,000 cap would become nearly irrelevant under that math — an 800 sq ft ADU would owe fees on 50 square feet proportionally, a figure far below the cap either way. The sub-750 exemption (already in WMC §3.62) survives; the proportional calculation at 750+ gets replaced by the marginal rule. We found no mention of SB 1117 in city materials; the January 2027 quarterly review will check for a revised park DIF guide. School fees are outside SB 1117’s impact-fee definition.
Disclaimer
Model estimate, not a quote. Fees change; the assumptions above are the city’s to confirm — the building permit under the new September 2025 fee schedule, the current school district fee for the parcel’s district, the water connection charge, and the transportation impact fee’s application to ADUs over 750 sq ft are all marked where they appear. Always verify current fees with the City of Westminster Community Development Department before budgeting.
*Floor, not a total: excludes the building permit and school district fee, which could not be verified from official sources at publication.