Published: 8 Nov 2026 · Last verified: 9 Oct 2026 · Next review: Jan 2027 Cost figures are re-checked against permit records quarterly. Changes are logged in Corrections.
Downey has a split personality, and Ordinance No. 23-1507 is the diagnosis. Below 750 square feet, the city waves ADUs through with zero impact fees. At 750 and above, the same project pays fees proportional to the primary dwelling — and gets its building permit through a valuation-based schedule that puts an 800 sq ft ADU around $4,972 before surcharges. It is the most generous cliff and one of the least generous permit counters in the series, in the same city.
Our six-phase total lands at $311,000, or $389 per square foot — a floor, not a total, marked with the asterisk where it appears. The permit example assumes a $150,000 valuation that the Building Official must ultimately set. The proportional impact fee (the base dwelling amounts are not published) and sewer/water capacity charges are marked “verify with city” and excluded from the total. Construction phases 2–6 are carried from the Los Angeles County baseline; Downey does not publish phase-level construction costs.
The short answer
| 800 sq ft detached ADU · Downey · 2026 | Amount |
|---|---|
| Total build cost (see assumptions) | $311,000* |
| Cost per square foot | $389 |
| Largest single line | Systems + interior, $147,000 |
| Building permit (example, $150K valuation) | ~$4,972 |
| DIF — $0 under 750; proportional at 750+ | not counted (verify with city) |
| School fee (Downey USD) | $4,136 (2024 rate cited by city) |
| Sewer / water capacity charges | not counted (verify with city) |
* Floor, not total: the proportional DIF amount and sewer/water capacity charges are excluded because we could not verify them. The permit figure assumes a $150,000 valuation set by the homeowner’s side of the counter — the city’s Building Official sets the final one.
The full line-item breakdown
Six phases. The same six used on every build in this series.
| Phase | Cost | Share |
|---|---|---|
| Soft costs (design, permits, fees) | $23,000 | 7% |
| Site work + foundation | $38,000 | 12% |
| Framing + structure | $48,000 | 15% |
| Building envelope | $42,000 | 14% |
| Systems + interior | $147,000 | 48% |
| Landscaping & hardscape | $13,000 | 4% |
| Total | $311,000* | $389 / sq ft |
The city’s fee lines are also listed on the Downey fee page, with verification status and source links.
The fee autopsy
Every fee line we found, with exactly what it is and where it came from.
| Fee line | Amount | Source / status |
|---|---|---|
| Design & engineering | $14,000 | Series baseline, carried (pre-approved plan program exists but had 0 registered plans as of Jul 28, 2026) |
| Building permit (valuation-based) | ~$4,972 | Proposed City User Fee Schedule FY 2026-2027, Section 6 (Building & Safety). Example: at assumed $150,000 valuation — $2,687.42 permit ($2,171.42 + $10.32 × 50) + 85% plan check ($2,284.31). Final valuation set by Building Official. Excludes $60.01 issuance, 8% technology fee, 0.013% SMIP (~$19.50), $6 building standards fee |
| DIF — ADU under 750 SF | $0 | Ordinance No. 23-1507, Municipal Code §9414.14(i) (adopted Jul 25, 2023) — mirrors state cliff |
| DIF — ADU 750 SF or larger | not counted | Same ordinance: “ADU area ÷ primary dwelling area × standard residential fee.” Standard dwelling fee amounts not published — verify with city |
| School fee (Downey USD) | $4,136 | $5.17/sq ft × 800 — City of Downey Building Permit Fee Schedule (effective 08/26/2024), quoting DUSD rate with “subject to change by the Downey Unified School District” note. DUSD’s own 2026 resolution (whether $5.38 applies) could not be found |
| Sewer capacity charge (LACSD) | not counted | LACSD FY26/27 rate table shows single-family $1,801/parcel but no ADU-specific rate line — ADU connection fee amount could not be found. Verify with city / LACSD |
| Water capacity charge (City Water Division) | not counted | Could not be found in official documents. Meter upgrade questions go to (562) 904-7246. Verify with city |
| Sewer/water policy (conversions) | $0 | Ord. 23-1507 §9414.14(j): converted ADUs/JADUs need no new connection and pay no capacity charges. New-construction ADUs (our example) need separate connection and pay proportionally |
The split personality: $0 impact fees, $4,972 permits
Read Ordinance 23-1507 in the morning and Downey looks like the most ADU-friendly city in the series. Section 9414.14(i) waives impact fees completely for ADUs under 750 square feet — cleaner than Chula Vista’s bulletin prose, since it is written straight into the municipal code. Conversion ADUs get the same generosity on utilities: no new connection, no capacity charges, $0.
Then take that same 800 sq ft project to the permit counter and the mood changes. The fee schedule is valuation-based with plan check at a full 85% of the permit fee — one of the steepest plan-check multipliers in the series. On our assumed $150,000 valuation that is $2,687.42 in permit fees and $2,284.31 in plan check, subtotal ~$4,972, and the surcharges (issuance, technology, SMIP, building standards) stack on top. The wrinkle is the valuation itself: the city does not publish a per-square-foot valuation for ADUs, so every homeowner’s number is a guess until the Building Official rules. The most certain thing on the fee sheet is the least certain thing about the project.
$4,136 school fees — with a 2024 asterisk
The school fee arithmetic is clean: $5.17 per square foot for the Downey Unified School District, from the city’s Building Permit Fee Schedule effective August 26, 2024 — $4,136 on 800 sq ft. The asterisk is the date. The city quotes DUSD’s rate with the explicit note that fees are “subject to change by the Downey Unified School District,” and DUSD’s own adopted 2026 resolution — which would show whether the state board’s $5.38 adjustment applies — could not be found online. Two years is a long time for a rate to sit still while the state ceiling moves. We count the city’s published $4,136, and flag the resolution as the item to confirm before budgeting.
The proportional DIF with no published base
Downey’s cliff formula is admirably explicit about the math and silent about the inputs. At 750 sq ft and above, the ADU pays “ADU area ÷ primary dwelling area × the standard residential fee” — a clean ratio, published in the ordinance. What the city does not publish is the standard residential fee for a new dwelling that the ratio multiplies against, so there is no dollar figure an 800 sq ft ADU can budget from the documents. This is the largest excluded unknown in the total, and the one most likely to move the number: a 1,600 sq ft primary dwelling would put the ADU at half the base rate; a 2,400 sq ft primary at a third. Settle the base amount with the city before doing any arithmetic.
Sewer and water: the proportional rule with no numbers
The ordinance sets the policy clearly: new-construction detached ADUs need their own sewer and water connections, and the connection fees and capacity charges scale proportionally with the ADU’s burden (area or fixture units). Downey’s water comes from the City Water Division, its sewer from the LA County Sanitation District — and neither publishes an ADU-specific dollar figure we could find. LACSD’s FY26/27 rate table lists single-family at $1,801 per parcel but has no ADU line at all; the LACSD application form has an ADU/JADU box to check, and then the price list goes quiet. Both lines stay excluded and marked “verify with city.”
Pre-approved plans: a program with no plans
Downey’s AB 1332 pre-approved standard plans program exists on the Building & Safety website — page, program name, legal basis, and as of July 28, 2026, zero registered plans. The city was actively soliciting design professionals, which means the program is a future benefit, not a current one. Every other pre-approved-plan city in the series pairs the plans with fee certainty; Downey pairs a promise of plans with the series’ most assumption-dependent permit. If the program fills its roster before the January 2027 review, this line gets rewritten.
Downey vs. Los Angeles County
| Downey | LA County baseline | |
|---|---|---|
| Total | $311,000* | $320,000 |
| Per sq ft | $389 | $400 |
| Building permit + plan check | ~$4,972 (assumed $150K valuation) | carried |
| DIF | $0 under 750; proportional at 750+ (amount not published) | carried |
| School fee | $4,136 (DUSD, 2024 rate) | $4,304 |
| Sewer / water capacity | proportional, amounts not found | carried |
| Pre-approved ADU plans | program exists, 0 plans registered | none |
The $9,000 gap to the baseline comes from soft costs — a valuation-example permit instead of an unknown, and a school fee one tier below the series max. The asterisk carries the real story: proportional DIF with no published base, and sewer/water charges with no published amounts, are the biggest exclusions in the series so far. Downey is the cheapest total we have published — and the least complete one.
A note on SB 1117
Signed September 2026, effective January 2027: for a homeowner’s first two ADUs, impact fees may apply only to square footage above 750, calculated marginally. See the full comparison at Downey: 2026 vs 2027, line by line. Downey’s ordinance-based proportional formula cannot survive that math unchanged — an 800 sq ft ADU would owe fees on 50 sq ft of proportional DIF, not 800, shrinking the cliff penalty to a sliver of its current size. We found no mention of SB 1117 in city materials; the January 2027 quarterly review will check for an amended Ordinance 23-1507. School fees are outside SB 1117’s impact-fee definition and stay at $4,136 pending DUSD’s resolution.
Disclaimer
Model estimate, not a quote. Fees change; the assumptions above are the city’s to confirm — the final building valuation, the proportional DIF base amounts, DUSD’s current adopted school-fee rate, and sewer/water capacity charges for ADUs are all marked where they appear. Always verify current fees with the City of Downey Building & Safety Division before budgeting.