Published: 7 Nov 2026 · Last verified: 7 Nov 2026 · Next review: Feb 2027 Cost figures are re-checked against permit records quarterly. Changes are logged in Corrections.
Redlands prices its ADU impact fees the way a grocer prices produce: by the pound, line by line, all from one document. Eight per-square-foot lines, one ordinance (Ord. 2968), $5.4405 per square foot in total — $4,352 on an 800 sq ft ADU. No flat fees, no pro-rata against the primary dwelling, no percentage of valuation. Every line carries a 751 sq ft minimum in the data, which means the 750 sq ft cliff is written into the fee schedule itself: build at 750 or under and all eight lines are $0. Our six-phase total lands at $309,000, or $386 per square foot — but it is a floor, not a finished figure. The school district fee and the building permit and plan-check fees are not yet verified, so they are not in the total at all.
The water lines are the surprise second act. Redlands charges $2.3657 per square foot for water capital improvements plus $0.6633 for water stocks and rights — $2,424 on our example — which is more than half the impact-fee total. Sewer adds $0.2696 per square foot ($216). Water and sewer together come to $2,640, the largest utility bill in this series so far for an 800 sq ft ADU. Construction phases 2–6 are carried from the Los Angeles County baseline; Redlands does not publish phase-level construction costs.
The short answer
| 800 sq ft detached ADU · Redlands · 2026 | Amount |
|---|---|
| Total build cost (floor — see gaps) | $309,000 |
| Cost per square foot | $386 |
| Largest single line | Systems + interior, $147,000 |
| Building permit + plan check | Not verified (gap) |
| Impact fees (8 lines, Ord. 2968) | $4,352 |
| School district fee | Not verified (gap) |
| Water / sewer | $2,640 |
| Pre-approved ADU plans | None found |
The full line-item breakdown
Six phases. The same six used on every build in this series.
| Phase | Cost | Share |
|---|---|---|
| Soft costs (design, permits, fees) | $21,000 | 7% |
| Site work + foundation | $38,000 | 12% |
| Framing + structure | $48,000 | 16% |
| Building envelope | $42,000 | 14% |
| Systems + interior | $147,000 | 48% |
| Landscaping & hardscape | $13,000 | 4% |
| Total | $309,000 | $386 / sq ft |
The fee autopsy
Every fee line we found, with exactly what it is and where it came from.
| Fee line | Amount | Source / status |
|---|---|---|
| Design & engineering | $14,000 | Series baseline, carried — no pre-approved ADU plan program found in city materials (absence not officially confirmed) |
| Open Space and Parks Fee | $943.52 | $1.1794/sq ft × 800 — Ord. 2968, min. 751 sq ft |
| Library Fee | $479.76 | $0.5997/sq ft × 800 — Ord. 2968, min. 751 sq ft |
| Storm Drain Facilities Fee | $409.04 | $0.5113/sq ft × 800 — Ord. 2968, min. 751 sq ft |
| Public Facilities Fee | $571.60 | $0.7145/sq ft × 800 — Ord. 2968, min. 751 sq ft |
| Fire Protection Facilities Fee | $360.24 | $0.4503/sq ft × 800 — Ord. 2968, min. 751 sq ft |
| Police Facilities Fee | $415.76 | $0.5197/sq ft × 800 — Ord. 2968, min. 751 sq ft |
| Transportation System Improvements Fee | $1,116.32 | $1.3954/sq ft × 800 — Ord. 2968, min. 751 sq ft |
| Solid Waste Capital Improvement Fee | $56.16 | $0.0702/sq ft × 800 — Ord. 2968, min. 751 sq ft |
| Impact fees, subtotal | $4,352.40 | $5.4405/sq ft × 800 — eight lines, all Ord. 2968 |
| Sewer Capital Improvement Fee | $215.68 | $0.2696/sq ft × 800 — Ord. 2968, min. 751 sq ft |
| Water Capital Improvement Fee | $1,892.56 | $2.3657/sq ft × 800 — Ord. 2968, min. 751 sq ft |
| Acquisition of Water Stocks and Water Rights Fee | $530.64 | $0.6633/sq ft × 800 — Ord. 2968, min. 751 sq ft |
| School district fee | not verified | No verified school-fee row on file for Redlands — not in the total |
| Building permit + plan check | not verified | No verified permit row on file for Redlands — not in the total |
Soft costs in the breakdown table are rounded to $21,000 (exact $20,992); the total is rounded to the nearest $1,000.
The city’s fee lines are also listed on the Redlands fee page, with verification status and source links.
Eight lines, one ordinance, one cliff
Every city in this series charges ADU impact fees, and most of them scatter the lines across several documents and several methods — flat, per-square-foot, pro-rata, percentage of valuation. Redlands puts all eight in Ordinance No. 2968, all per-square-foot, all with a 751 sq ft minimum. Open Space and Parks ($1.1794) and Transportation ($1.3954) together are $2.5748 per square foot — 47% of the $5.4405 total. The smallest line, Solid Waste at $0.0702, is $56.16 on our example: real money, but barely a rounding error against the whole.
The practical effect is a clean cliff. State law (Gov. Code §66311.5) already zeroes impact fees at 750 sq ft or less, but in most cities the cliff has to be assembled from a mix of flat and per-square-foot lines, some of which need converting. In Redlands the ordinance does the work: every line starts at 751 sq ft. Build at 750 and the impact-fee total is $0; build at 800 and it is $4,352.40. There is no ambiguity to argue with the counter about.
Water is the second-biggest fee
The water lines deserve their own paragraph because they are easy to miss and hard to ignore. Water Capital Improvement ($2.3657/sq ft) is the single largest per-square-foot rate in Redlands after Transportation — and the Acquisition of Water Stocks and Water Rights fee ($0.6633/sq ft) is a line no other city in this series charges. Together they are $2,423.20 on 800 sq ft. Add the Sewer Capital Improvement fee ($215.68) and water and sewer come to $2,638.88 — the largest utility bill we have published for an 800 sq ft ADU.
Unlike impact fees, water and sewer charges are not covered by SB 1117. Connection and capacity charges stay as the city sets them, and the 750 sq ft cliff does not apply to them. The 2027 rule changes the impact-fee column only.
Two gaps that matter
This total is a floor, and the two gaps are the reason. We have no verified school district fee for Redlands: the Redlands Unified School District rate is not in our data, and at the $5.38 state maximum it would add $4,304. We have no verified building permit or plan-check fee either — no rate table, no flat fee, nothing to price. Both are real costs a homeowner will pay; neither is in the $309,000. When they are verified, this post will be updated and the total will rise.
Redlands vs. Los Angeles County
| Redlands | LA County baseline | |
|---|---|---|
| Total | $309,000 (floor) | $320,000 |
| Per sq ft | $386 | $400 |
| Building permit + plan check | Not verified | carried |
| Impact fees | $4,352 (8 lines, Ord. 2968) | carried |
| School fee | Not verified | $4,304 |
| Water / sewer | $2,640 | carried |
| Pre-approved ADU plans | None found | none |
The $11,000 gap to the baseline is the two missing fees, not a cheaper build. If the school fee lands at the $5.38 maximum and the permit fees land near the series norm, Redlands will sit at or above the baseline. The real story is the composition: the cleanest impact-fee schedule in the series, the heaviest water bill, and a total that is honest about what it does not yet know.
A note on SB 1117
Signed September 2026, effective January 2027: for a homeowner’s first two ADUs, impact fees may apply only to square footage above 750, calculated marginally. Redlands is the cleanest case in the series for this rule — every impact line is per-square-foot, so the 2027 saving is exactly 750 × $5.4405, about $4,080 on an 800 sq ft ADU. See the full comparison at Redlands: 2026 vs 2027, line by line. School fees, permit fees and water/sewer charges are outside SB 1117’s impact-fee definition and do not change.
Disclaimer
Model estimate, not a quote. Fees change; the assumptions above are the city’s to confirm — the school district fee and the building permit and plan-check fees are not yet verified and are marked where they appear. Always verify current fees with the City of Redlands before budgeting.