Burbank ADU Fees 2026: The $3,692 Permit and a Sewer Cliff

Edit page

In this series

Every build below uses the same six-phase ledger, so you can compare any two directly.

New construction

Geography

Compare any two builds side by side →

Published: 7 Oct 2026 · Last verified: 12 Nov 2026 · Next review: Jan 2027 Cost figures are re-checked against permit records quarterly. Changes are logged in Corrections.

Burbank is the first city in this series to put a 750 sq ft cliff on the sewer bill — and the first to write ADU-specific fees directly into its official fee schedule. Those two bureaucratic details tell you most of what you need to know about building here.

The sewer facilities charge — $2,043 per residence — carries a footnote that reads like it was written for this series: ADUs greater than 750 square feet pay a proportional share based on an 1,800 sq ft average household. An 800 sq ft ADU clearing the cliff pays $908. Below it, $0. No other city we have published draws the state-law line on sewer. Meanwhile the fee schedule lists “Accessory Dwelling Unit” as its own line item twice — $1,728.42 for the Planning application and $273.95 for the Public Works plan check review — the first time ADU has appeared as a named fee anywhere in this series. Our six-phase total lands at $320,000, or $400 per square foot — exactly the LA County baseline, built from very different parts.

Four assumptions sit underneath that total, each marked where it appears: whether the Planning ADU fee applies to a ministerial permit, whether a detached ADU needs a separate water connection, the final adoption of the ADU ordinance update, and the parks allocation inside the community facilities fee. Construction phases 2–6 are carried from the Los Angeles County baseline; Burbank does not publish phase-level construction costs.

The short answer

800 sq ft detached ADU · Burbank · 2026Amount
Total build cost (see assumptions)$320,000
Cost per square foot$400
Largest single lineSystems + interior, $147,000
Building permit + plan check$3,692 (highest in the series)
School district fee (single district)$4,304 ($5.38 rate, Resolution 1-27)
DIF — transportation + community facilities, pro-rata~$7,078 (assumed)
Sewer facilities charge, pro-rata (750+ only)$908
ADU-specific schedule fees (Planning + Public Works)~$2,002

The full line-item breakdown

Six phases. The same six used on every build in this series.

PhaseCostShare
Soft costs (design, permits, fees)$32,00010%
Site work + foundation$38,00012%
Framing + structure$48,00015%
Building envelope$42,00013%
Systems + interior$147,00046%
Landscaping & hardscape$13,0004%
Total$320,000$400 / sq ft

The city’s fee lines are also listed on the Burbank fee page, with verification status and source links.

The fee autopsy

Every fee line we found, with exactly what it is and where it came from.

Fee lineAmountSource / status
Design & engineering$14,000Series baseline, carried (BPAP plans are purchased from designers, not free)
Building permit (R-3 Type B)$2,142$1,647.14 + 3 × $165.02 per 100 sq ft over 500 — FY 2026-27 adopted fee schedule
Plan check (R-3 Type B)$1,550$1,193.28 + 3 × $118.77 per 100 sq ft over 500 — same schedule
Planning — ADU application$1,728“Accessory Dwelling Unit” line item, Art. III §1(C)(6) — the standard ADU permit application fee; applies to ministerial permits (BMC 10-1-620.7(A)(4))
Public Works — ADU plan check review$274“Accessory Dwelling Unit (ADU) Plan Check Reviews” line item
School fee (Burbank USD)$4,304$5.38/sq ft × 800 — BUSD Resolution 1-27, adopted 6 Aug 2026, effective 5 Oct 2026
DIF — transportation + community facilities, pro-rata (example)~$7,078$15,166.33 × 800/1,800 + 5% surcharge — per the city’s published ADU DIF calculation guide
Sewer facilities charge, pro-rata$908$2,043 × 800/1,800 — footnote (e): ADUs over 750 sq ft only
Water connection$0Existing connection used — whether a detached ADU requires a separate connection is unconfirmed (BWP discretion)

The sewer cliff: a series first

Every city in this series honors the 750 sq ft cliff on development impact fees — state law (Gov. Code §66311.5) leaves no choice. Burbank goes further: its sewer facilities charge carries the same line. Footnote (e) to the $2,043 single-family residential rate reads, in full: “Accessory Dwelling Units (ADU) greater than 750 square feet will be assessed a proportional sewer facilities charge based on the single-family residential rate and average household size of 1,800 square feet.”

The practical effect: a 749 sq ft ADU pays $0 in sewer facilities charges; an 800 sq ft ADU pays $908. In every other city we have published, sewer is either flat, waived for ADUs sharing services, or silent on the threshold. Burbank is the only one to write the cliff into the sewer line itself — which means an 800 sq ft design here clears two cliffs at once, DIF and sewer, for a combined ~$7,986 before a single school fee is counted.

ADU, itemized: fees with the unit’s name on them

Burbank’s FY 2026-27 fee schedule names “Accessory Dwelling Unit” twice. The Planning section lists an ADU application at $1,728.42; the Public Works section lists an ADU plan check review at $273.95. No other city in this series has ADU as a named fee line — elsewhere the unit is processed under generic residential tiers and the schedule never says the word.

The $1,728 is confirmed, not assumed. BMC 10-1-620.7(A) requires every ADU applicant to file the ADU permit application with the Planning Division and pay the application fee in the Adopted Citywide Fee Schedule, and BMC 10-1-620.3(A) requires complete applications to be approved or denied ministerially within 60 days — the fee is part of the ministerial application itself. The schedule lists it as its own line item, Art. III §1(C)(6), not the (C)(1) Pre-Development Review fee ($4,676.54). We count it in the total as verified.

The most expensive permit in the series

Burbank’s building permit plus plan check, at $3,692 for our 800 sq ft example, is the highest in the series — 2.2× Anaheim’s $1,672, which bundles both into a single combined fee. The R-3 Type B wood-frame tier starts at $1,647.14 for the first 500 sq ft and adds $165.02 per additional 100; plan check adds $1,193.28 plus $118.77 per 100 over 500. There is no combined-permit discount here, and no percentage-of-permit plan check either — just two long tier tables, both fully priced.

BPAP: pre-approved, but not free

The Burbank Pre-Approved ADU Program sounds like Anaheim’s ADU Express until you read the second sentence. Designers register their plans with the city; the city publishes them in a library; homeowners buy the plans from the designer. The current library holds two designs — a 432 sq ft city-registered studio and a 360 sq ft LADBS-approved studio. Garden Grove hands out four city-produced plans free; Anaheim hands out four free with a seven-step pipeline. Burbank’s model outsources the design cost to a marketplace, which is why our $14,000 design line stays at the series baseline instead of dropping toward zero.

The 750 cliff (DIF)

Burbank’s ordinance states the rule plainly (BMC 10-1-620.3(K)(2)): no development impact fees under 750 sq ft; proportional fees above. The city’s published calculation guide pins down the method — interior livable space per SB 543, ADU square footage divided by the primary dwelling’s, house size verified against the LA County Assessor portal. On an 1,800 sq ft house, an 800 sq ft ADU pays 44.4% of the $15,166.33 combined transportation-plus-community-facilities rate, plus the 5% administration surcharge: ~$7,078. On a 1,500 sq ft house the same ADU pays ~$8,493 — the primary dwelling’s size, not the ADU’s, is the lever.

The school-fee cliff sits lower at 500 sq ft (SB 543), so the 800 sq ft example pays school fees on the full area either way.

Burbank vs. Los Angeles County

BurbankLA County baseline
Total$320,000$320,000
Per sq ft$400$400
Building permit + plan check$3,692 (series high)carried
DIF (pro-rata example)~$7,078carried
Sewer facilities charge$908 (750 cliff)carried
School fee$4,304 (single district)$4,304
ADU-named schedule fees$2,002none
Pre-approved plans2, paid registrynone
ADU permits 2022–2024 (HCD)818, 14th statewide—

The $0 gap is a coincidence of the example math, not a finding — the four unconfirmed assumptions dominate it. The real story is the composition: the series’ only sewer cliff, its only ADU-named fees, and its most expensive permit, all netting to exactly the baseline.

A note on SB 1117

Signed September 2026, effective January 2027: for a homeowner’s first two ADUs, impact fees may apply only to square footage above 750, calculated marginally. See the full comparison at Burbank: 2026 vs 2027, line by line. Burbank’s ADU-to-house pro-rata DIF and its proportional sewer charge will both need rewrites — an 800 sq ft ADU would owe fees on 50 sq ft, not 800. We found no mention of SB 1117 in city materials; the January 2027 quarterly review will check for an updated ordinance.

Disclaimer

Model estimate, not a quote. Fees change; the assumptions above are the city’s to confirm — the Planning ADU fee’s applicability, water connection requirements, the ordinance update’s final adoption, and the parks allocation are all marked where they appear. Always verify current fees with the City of Burbank Community Development Department before budgeting.

Frequently asked questions

How much does an ADU cost in Burbank in 2026?

About $320,000 for an 800 sq ft detached, single-story, new-construction unit with mid-grade finishes in Burbank — roughly $400 per square foot, at parity with the LA County baseline. That figure rests on four stated assumptions we have not confirmed with the city: whether the $1,728 Planning ADU fee applies to a ministerial permit, whether a detached ADU needs a separate water connection, the final adoption of the ADU ordinance update, and the parks allocation inside the community facilities fee. Construction phases 2–6 are carried from the Los Angeles County baseline; Burbank does not publish phase-level construction costs.

Does Burbank charge impact fees on ADUs?

ADUs under 750 square feet are fully exempt under state law (Gov. Code §66311.5), and Burbank's ordinance (BMC 10-1-620.3(K)(2)) says so explicitly. ADUs of 750 square feet or more pay impact fees proportional to the primary dwelling's square footage — the city's published DIF calculation guide uses the ADU-to-house ratio with the house size taken from the LA County Assessor portal. Our example math puts an 800 sq ft ADU's share at about $7,078 on an 1,800 sq ft house, including the 5% administration surcharge.

How much are school district fees on an ADU in Burbank?

$4,304 on 800 sq ft at $5.38 per square foot. The Burbank Unified School District board adopted Resolution 1-27 on August 6, 2026 (unanimous vote, agenda item 12.a), and the $5.38 rate took effect October 5, 2026. The district's May 2026 justification study is the first in this series to name ADUs directly, stating that 'ADUs and JADUs over 500 square feet' generate students and will be levied. Burbank is a single-district city, so there is no split to track.

Does Burbank have pre-approved ADU plans?

Yes, but not free ones. The Burbank Pre-Approved ADU Program (BPAP) is a designer registry: architects register their plans, the city lists them in a public library (currently two designs), and homeowners buy the plans from the designer. That contrasts with Garden Grove and Anaheim, which hand out city-produced plans for free. Registration review and permit review each target 30 business days.

New line-item breakdowns and quote-check tips by email

Occasional emails when a new cost breakdown goes up. No contractor leads. Unsubscribe anytime.


Edit page
Share this post:

Previous Post
Anaheim ADU Fees 2026: The Series' Highest Impact Fees
Next Post
Torrance ADU Cost 2026: $317,000 With the Series' First Flat-Rate ADU Impact Fee