Burlingame ADU Cost 2026: $309,000–$310,000 Floor — Water and Sewer Capacity Priced per Square Foot, Basis Unclear

Edit page

In this series

Every build below uses the same six-phase ledger, so you can compare any two directly.

New construction

Geography

Compare any two builds side by side →

Published: 7 Nov 2026 · Last verified: 7 Nov 2026 · Next review: Feb 2027 Cost figures are re-checked against permit records quarterly. Changes are logged in Corrections.

Burlingame’s ledger has a hole in the middle of it, and the hole is a single ambiguous phrase. Water capacity is $3.04 per square foot and sewer capacity is $4.63 per square foot, both charged “over 150 sq ft” — but the fee schedule does not settle whether the assessable basis is the 650 sq ft above 150 or the full 800 sq ft. Water is $1,976 on the first reading and $2,432 on the second; sewer is $3,009.50 and $3,704. That one ambiguity moves the total by $1,150.50, so the ledger is a range: $309,000–$310,000, or $386–$388 per square foot — and it is a floor, not a finished figure. The school district fee and the general building permit fee are not yet verified, so they are not in the total at all.

What is verified is itemised and ordinary. The planning application fee is $950. Plumbing, mechanical and electrical permits are $729 — three permits at $0.18 per square foot plus a $99 issuance fee each. The Affordable Housing Impact Fee is $0 for a single detached ADU. The 0.2% General Plan maintenance fee is a verified rate, but it is a percentage of building valuation and no valuation basis is on file, so it is not counted. Construction phases 2–6 are carried from the Los Angeles County baseline; Burlingame does not publish phase-level construction costs.

The short answer

800 sq ft detached ADU · Burlingame · 2026Amount
Total build cost (floor — see gaps)$309,000–$310,000
Cost per square foot$386–$388
Largest single lineSystems + interior, $147,000
Building permit + plan check$729 (trade permits only — general permit not verified)
Impact fees$0
School district feeNot verified (gap)
Water / sewer capacity$4,986–$6,136
Pre-approved ADU plansNone found

The full line-item breakdown

Six phases. The same six used on every build in this series. Illustrations (not quotes).

PhaseCostShare
Soft costs (design, permits, fees)$21,000–$22,0007%
Site work + foundation$38,00012%
Framing + structure$48,00016%
Building envelope$42,00014%
Systems + interior$147,00048%
Landscaping & hardscape$13,0004%
Total$309,000–$310,000$386–$388 / sq ft

The fee autopsy

Every fee line we found, with exactly what it is and where it came from.

Fee lineAmountSource / status
Design & engineering$14,000Series baseline, carried — no free city pre-approved plans found; the city points homeowners to the San Mateo County ADU Resource Center for floor plan ideas, and its AB 1332 preapproval program is for design professionals, whose plans applicants pay to use (absence of a free city program not officially confirmed)
Water capacity charge, detached ADU over 150 sq ft$1,976–$2,432$3.04/sq ft — Master Fee Schedule FY2024-25; basis ambiguous (650 sq ft over 150 vs full 800 sq ft)
Sewer capacity charge, detached ADU over 150 sq ft$3,009.50–$3,704$4.63/sq ft — Master Fee Schedule FY2024-25; basis ambiguous, same two readings
ADU planning application fee$950FY2024-25 Master Fee Schedule and ADU submittal packet; ministerial processing, no design-review fee for a compliant ADU
Plumbing, mechanical and electrical permits (new residential)$7293 × ($144 + $99) — $0.18/sq ft + $99 issuance per trade; before any 25% plan-review add-on
General Plan / Title 25 maintenance feenot counted0.2% of building valuation — verified rate, but no valuation basis on file, so not in the total
Categorical Exemptionnot counted$141 — shown in the ADU submittal packet’s $1,091 example total with the $950 application fee; not a separate verified fee row, so not in the total
Affordable Housing Impact Fee$0Applies only to commercial linkage and multifamily at scale (11+ rental / 7+ for-sale units)
School district feenot verifiedNo verified school-fee row on file for Burlingame — not in the total
General building permitnot verifiedOnly the trade permits are verified; no general building permit row on file — not in the total

Soft costs in the breakdown table are rounded to $21,000–$22,000 (exact $20,664.50–$21,815); the totals are rounded to the nearest $1,000.

The city’s fee lines are also listed on the Burlingame fee page, with verification status and source links.

The $1,150.50 question

The capacity charges are the whole story of this ledger, and they turn on four words: “over 150 sq ft”. The schedule prices water capacity at $3.04 per square foot and sewer capacity at $4.63 per square foot for a detached ADU over 150 sq ft. On the natural reading, only the area above 150 sq ft is assessed — 650 sq ft — giving water $1,976 and sewer $3,009.50. On the other reading, the full 800 sq ft is assessed, giving water $2,432 and sewer $3,704. The difference is $456 on water and $694.50 on sewer: $1,150.50 in total, which is exactly the width of the range in this post.

Both readings are recorded as confirmed figures because the rate itself is confirmed and the schedule does not fix the basis. The basis is due to be fixed on December 1, when this post will be updated to a single figure. Until then, the honest total is a range — and a homeowner budgeting at the low end should know the high end is $1,150.50 away.

Two gaps that matter

This total is a floor, and the two gaps are the reason. We have no verified school district fee for Burlingame: the city sits across two school districts, and neither rate is in our data. At the $5.38 state maximum, a school fee would add $4,304. We have no verified general building permit fee either — only the three trade permits at $729 are priced, and the 0.2% General Plan maintenance fee cannot be computed without a valuation basis. The ADU submittal packet shows a $1,091 example total ($950 application fee plus a $141 Categorical Exemption), which hints at the shape of the permit column, but a packet example is not a fee schedule line, so the $141 stays out of the total. Both gaps are real costs a homeowner will pay; neither is in the $309,000–$310,000. When they are verified, this post will be updated and the total will rise.

Burlingame vs. Los Angeles County

BurlingameLA County baseline
Total$309,000–$310,000 (floor)$320,000
Per sq ft$386–$388$400
Building permit + plan check$729 (trade permits only)carried
Impact fees$0carried
School feeNot verified$4,304
Water / sewer capacity$4,986–$6,136carried
Pre-approved ADU plansNone foundnone

The gap to the baseline is the two missing fees, not a cheaper build. If the school fee lands at the $5.38 maximum and the general permit lands near the series norm, Burlingame will sit at or above the baseline. The real story is the composition: the only capacity charges in the series priced per square foot with an unsettled basis, a $950 planning fee with no design-review fee, and a total that is honest about what it does not yet know.

A note on SB 1117

Signed September 2026, effective January 2027: for a homeowner’s first two ADUs, impact fees may apply only to square footage above 750, calculated marginally. Burlingame’s only impact-fee line is already $0, so SB 1117 changes nothing we can compute here — there is nothing to reduce. See the full comparison at Burlingame: 2026 vs 2027, line by line. School fees, permit fees and water/sewer charges are outside SB 1117’s impact-fee definition and do not change.

Disclaimer

Model estimate, not a quote. Fees change; the assumptions above are the city’s to confirm — the school district fee and the general building permit fee are not yet verified, and the water and sewer capacity basis is ambiguous; all are marked where they appear. Always verify current fees with the City of Burlingame before budgeting.

Frequently asked questions

How much does an ADU cost in Burlingame in 2026?

About $309,000–$310,000 for an 800 sq ft detached, single-story, new-construction unit with mid-grade finishes in Burlingame — roughly $386–$388 per square foot. The range comes from the water and sewer capacity charges, whose assessable basis is ambiguous in the fee schedule. That total is a floor: the school district fee and the general building permit fee are not yet verified, so they are not in the total. Construction phases 2–6 are carried from the Los Angeles County baseline; Burlingame does not publish phase-level construction costs.

Why is the Burlingame total a range?

Water capacity is $3.04 per square foot and sewer capacity is $4.63 per square foot, both 'over 150 sq ft' — but the schedule does not settle whether the assessable basis is the 650 sq ft above 150 or the full 800 sq ft. Water is $1,976 on the first reading and $2,432 on the second; sewer is $3,009.50 and $3,704. The $1,150.50 spread is the whole range in the total. The basis is due to be fixed on December 1.

Does Burlingame charge impact fees on an ADU?

No. The Affordable Housing Impact Fee is $0 for a single detached ADU — it applies only to commercial linkage and multifamily at scale (11 or more rental units, 7 or more for-sale units). Because the impact fee is already $0, SB 1117 has nothing to reduce here.

New line-item breakdowns and quote-check tips by email

Occasional emails when a new cost breakdown goes up. No contractor leads. Unsubscribe anytime.


Edit page
Share this post:

Previous Post
Concord ADU Cost 2026: $313,000–$316,000 Floor — Flat-Band Impact Fees and Six Free Pre-Approved Plans
Next Post
Watsonville ADU Cost 2026: $308,000 Floor — Three $0 Impact Fees, Each with Its Own Threshold

Keep reading

Calculate your exact fees →