Published: 7 Nov 2026 · Last verified: 7 Nov 2026 · Next review: Feb 2027 Cost figures are re-checked against permit records quarterly. Changes are logged in Corrections.
Concord’s impact fees come in a band, not a line. The Off-Site Street Improvement Program (OSIP) and the Park Land fee are flat amounts for ADUs of 750–1,200 sq ft, and each has two tiers: OSIP is $1,073 or $1,626, Park Land is $5,508 or $8,345, depending on whether the ADU exceeds 40% of the primary dwelling. For an 800 sq ft ADU, the boundary is a 2,000 sq ft primary home — and the size of the house already on the lot is the one thing this ledger cannot know. That single unknown moves the total by $3,000, so the ledger is a range: $313,000–$316,000, or $391–$395 per square foot. And it is a floor: the building permit fee is not yet verified, so it is not in the total at all.
The offset is real. Concord offers six free city pre-approved ADU plans, from a 205 sq ft efficiency studio to an 874 sq ft two-bedroom, with typical plan-check fees waived and permits possible within five working days for a complete submittal. The school fee is $4,136 from Mt. Diablo Unified at $5.17 per square foot — the 2024-25 study rate, with no 2026 increase published. Planning is $0: ADUs are reviewed ministerially. The sewer application fee is $157; the sewer capacity fee itself is unverified and not in the total. Construction phases 2–6 are carried from the Los Angeles County baseline; Concord does not publish phase-level construction costs.
The short answer
| 800 sq ft detached ADU · Concord · 2026 | Amount |
|---|---|
| Total build cost (floor — see gaps) | $313,000–$316,000 |
| Cost per square foot | $391–$395 |
| Largest single line | Systems + interior, $147,000 |
| Building permit + plan check | Not verified (gap) |
| Impact fees (OSIP + Park Land) | $6,581–$9,971 |
| School district fee (MDUSD) | $4,136 |
| Sewer connection application | $157 |
| Pre-approved ADU plans | 6 free city plans |
The full line-item breakdown
Six phases. The same six used on every build in this series. Illustrations (not quotes).
| Phase | Cost | Share |
|---|---|---|
| Soft costs (design, permits, fees) | $25,000–$28,000 | 8% |
| Site work + foundation | $38,000 | 12% |
| Framing + structure | $48,000 | 15% |
| Building envelope | $42,000 | 13% |
| Systems + interior | $147,000 | 47% |
| Landscaping & hardscape | $13,000 | 4% |
| Total | $313,000–$316,000 | $391–$395 / sq ft |
The fee autopsy
Every fee line we found, with exactly what it is and where it came from.
| Fee line | Amount | Source / status |
|---|---|---|
| Design & engineering | $14,000 | Series baseline, carried — the city offers six free pre-approved plans (see below); using one can cut this line, but a site plan and site-specific engineering still apply, so the full baseline stays in the total |
| School fee (Mt. Diablo USD, Level I) | $4,136 | $5.17/sq ft × 800 — MDUSD 2024-25 Developer Fee Justification Study (board hearing 8/28/2024); no 2026 increase published |
| Off-Site Street Improvement Program (OSIP), ADU 750–1,200 sq ft | $1,073–$1,626 | FY2025-26 master fee schedule, Res. 25-6042.3, items 28.1.1–28.1.2; $1,626 if ADU exceeds 40% of primary dwelling, $1,073 if 40% or smaller; $0 below 750 sq ft |
| Park Land fee, ADU 750–1,200 sq ft | $5,508–$8,345 | FY2025-26 master fee schedule, items 31.5–31.6; $8,345 (50% of $16,691 low-density designation) if ADU exceeds 40% of primary, $5,508 if 40% or smaller; $0 below 750 sq ft |
| Impact fees, subtotal | $6,581–$9,971 | OSIP + Park Land, both flat-band |
| ADU planning fee | $0 | No ADU planning fee anywhere in the 5,777-line FY2025-26 adopted schedule; ADUs reviewed ministerially within 60 days |
| Sewer connection application processing fee | $157 | FY2025-26 master fee schedule, item 37.1; distinct from the sewer capacity fee, which is unverified for ADUs and not in the total |
| Building permit + plan check | not verified | No verified permit row on file for Concord — not in the total |
Soft costs in the breakdown table are rounded to $25,000–$28,000 (exact $24,874–$28,264); the totals are rounded to the nearest $1,000.
The city’s fee lines are also listed on the Concord fee page, with verification status and source links.
The 40% line
The tier rule is the whole story of this ledger, and it is worth reading slowly. Both impact fees are flat amounts for ADUs of 750–1,200 sq ft — not per-square-foot, not a percentage of valuation. Each fee has two tiers, and the tier is decided by one ratio: the ADU’s size against the primary dwelling. If the ADU exceeds 40% of the primary dwelling, OSIP is $1,626 and Park Land is $8,345. If it is 40% or smaller, OSIP is $1,073 and Park Land is $5,508. For an 800 sq ft ADU, the boundary is a 2,000 sq ft primary home: a 1,900 sq ft house puts you in the high tier, a 2,100 sq ft house puts you in the low tier, and the difference is $3,390 across the two fees.
Both tiers are recorded as confirmed figures because the fee schedule does not fix the primary dwelling’s size — the schedule gives the rule, not the answer for a particular lot. And both fees are $0 below 750 sq ft, which is the cliff doing its work: build at 750 and the impact-fee total is $0; build at 800 and it is $6,581–$9,971. The cliff is written into the band itself.
Six free plans, and the rebate that just closed
Concord’s free-plan program is the most complete in this series so far. Six construction-level designs the city already approved — a 205 sq ft efficiency studio, a 394 sq ft studio, three one-bedroom designs at 627, 650 and 709 sq ft, and an 874 sq ft two-bedroom — in multiple architectural styles (Bungalow/Craftsman, Spanish-inspired, post-war suburban rancher, modern). There is no cost for design fees and typical plan-check fees are waived; the applicant provides a basic site plan, and hourly plan-check fees apply to the review of that. A complete site-specific submittal can be issued within five working days.
The same program used to come with cash. Concord ran an ADU rebate program, funded by a $277,226 California Housing Finance Agency grant, offering up to $15,000 for income-restricted units or up to $7,500 for market-rate units — but applications closed on September 30, 2026, and the funding was first-come, first-served. This ledger does not count the rebate, because the window has closed. Ask the city whether any new incentives are available before budgeting around one.
The one gap in this ledger sits next to the free plans. The building permit and plan-check fee is not verified — no rate table, no flat fee, nothing to price. The free plans waive typical plan-check fees, which softens the gap, but the permit fee itself is a real cost a homeowner will pay, and it is not in the $313,000–$316,000. When it is verified, this post will be updated and the total will rise.
Concord vs. Los Angeles County
| Concord | LA County baseline | |
|---|---|---|
| Total | $313,000–$316,000 (floor) | $320,000 |
| Per sq ft | $391–$395 | $400 |
| Building permit + plan check | Not verified | carried |
| Impact fees | $6,581–$9,971 (flat band) | carried |
| School fee | $4,136 (2024-25 rate) | $4,304 |
| Sewer | $157 (application only) | carried |
| Pre-approved ADU plans | 6 free city plans | none |
The gap to the baseline is the missing permit fee, not a cheaper build. If the permit fee lands near the series norm, Concord will sit at or above the baseline. The real story is the composition: the only flat-band impact fees in the series, a school fee still on its 2024-25 rate, and the most complete free-plan program we have published — with a rebate window that has already closed.
A note on SB 1117
Signed September 2026, effective January 2027: for a homeowner’s first two ADUs, impact fees may apply only to square footage above 750, calculated marginally. Concord’s impact fees are flat amounts in a 750–1,200 sq ft band, and the city has not published how a flat band converts to a marginal charge on the 50 sq ft above 750 — so no 2027 saving is computed here. The 2027 treatment of flat-band fees is uncertain, and this post will not guess at it. See the full comparison at Concord: 2026 vs 2027, line by line. School fees, permit fees and sewer charges are outside SB 1117’s impact-fee definition and do not change.
Disclaimer
Model estimate, not a quote. Fees change; the assumptions above are the city’s to confirm — the building permit and plan-check fee is not yet verified and is marked where it appears, and the impact-fee tiers depend on the primary dwelling’s size. Always verify current fees with the City of Concord before budgeting.