Published: 23 Nov 2026 · Last verified: 13 Nov 2026 · Next review: Dec 2026 This ranking updates monthly as new city posts publish. All figures are 800 sq ft detached ADU, 2026. Changes logged in Corrections.
Twenty cities. Same 800 sq ft detached ADU. Same mid-grade finishes. $44,000 apart on paper — from Salinas (~$300,000*) to San Diego ($344,000).
But read the asterisks first. Among the 15 cities with firm totals, the spread has widened since Day 25’s table: about $14,000 — Oceanside ($311,000) to San Francisco ($325,000), with San Diego ($344,000) still the outlier. The headline widening comes from five preliminary totals, each marked honestly. The thesis hasn’t changed: the spread lives in Phase 1 — the soft costs. Construction barely moves between these cities.
The ranking
| Rank | City | Total (800 sq ft) | Per sq ft | Key fee line |
|---|---|---|---|---|
| 1 | Salinas | ~$300,000* | $375 | DIF $0 (series first full waiver) |
| 2 | Fontana | ~$305,000* | $381 | Preliminary — see post |
| 3 | Santa Maria | $306,000* | $383 | Sewer charged proportionally (series only) |
| 4 | Chula Vista | $308,000 | $385 | Flat-fee ADU permit ~$3,951 |
| 5 | Riverside | $309,000 | $386 | Permit $1,006 (series low); free 800 sq ft plans |
| 6 | Lakewood | ~$310,000* | $388 | Preliminary — see post |
| 7 | Pasadena | ~$310,000 | $388 | School $1,792 (series low) |
| 8 | Oceanside | $311,000 | $389 | DIF $0 |
| 9 | Long Beach | $313,000 | $391 | School $4,304 |
| 10 | Palo Alto | ~$313,000 | $391 | DIF ~$18,090 (FY27, proportional); permit ~$5,790 |
| 11 | Sacramento | $316,000 | $395 | School $4,104 |
| 12 | San Bernardino | ~$316,000* | $395 | Preliminary — see post |
| 13 | Torrance | $317,000 | $396 | DIF $2,243.47 (series low); school $4,304 |
| 14 | Campbell | ~$318,000 | $398 | School ~$4,304 |
| 15 | Fullerton | $318,000 | $398 | Permit $1,223 (cheapest at publication) |
| 16 | Anaheim | $320,000 | $400 | DIF ~$10,411* (series high) |
| 17 | Burbank | $320,000 | $400 | Permit + plan check $3,692 |
| 18 | Oakland | $322,000 | $403 | Permit $12,800–$19,200 |
| 19 | San Francisco | $325,000 | $406 | Permit ~$19,500 |
| 20 | San Diego | $344,000 | $430 | Highest soft-cost stack in the series |
* Asterisked totals carry stated assumptions or unverified items — see each city’s post for the full ledger. Palo Alto’s total is marked without an asterisk because the correction is published, but the post notes remaining line items.
What changed since Day 25
Ten cities added. The Day 25 table ranked 10; this edition doubles it. The biggest movers in the story:
- The floor dropped. Santa Maria ($306,000*) was already the nominal low in v1 but excluded for unverified items. Now five asterisked preliminary entries reach lower — Salinas at ~$300,000* on the back of a full DIF waiver — and Palo Alto at ~$313,000 after correcting a widely-circulated bad number, now level with Long Beach rather than undercutting it.
- The Palo Alto correction. Batch-matrix research caught a real error: DIF was rumored at ~$76,000 and permits at 5.42%. Both wrong. DIF is
$18,090 on the FY27 sheet (proportional, as of August 17, 2026); permits are 1.76% ($5,790). The corrected total is level with Long Beach at the low end of the firm totals, not the series high it was assumed to be. - The Oceanside correction. Oceanside’s permit was listed at ~$7,541 from 2018/2021 rate tables; the published FY 2026-27 schedule prices plan check ($1,862.70) plus inspection ($3,515.40) at $5,378.10, cutting the city’s total to $311,000 — now the lowest firm total in this table, undercutting Long Beach.
- San Diego is still the outlier. At $344,000, it sits $19,000 above San Francisco — more than the entire rest of the firm spread combined. Its soft-cost stack, not its construction cost, explains the gap.
What the spread tells you
Among firm totals, $14,000 is the story — and it’s small. Just over 4% of a $320,000 build. Nobody should pick a city for ADU fees alone. But $14,000 is also real money, and it concentrates in lines you can plan around:
- School fees are the most predictable spread: $1,792 (Pasadena) to ~$4,304 (Campbell). District boundaries, not city boundaries, set this number.
- Impact fees are the most volatile: $0 (Salinas, Oceanside, Oakland) to ~$10,411 (Anaheim’s DIF).
- Permit fees are the least predictable: $1,006 (Riverside) to ~$19,500 (San Francisco). Valuation-based cities punish expensive builds; flat-fee cities don’t.
- The DIF waiver trend is accelerating. Salinas (full waiver), Oceanside, Fremont, Santa Monica — more cities are dropping DIF to $0 for ADUs. This is the single biggest driver of the new low-end entries.
The cliff still matters more than the ranking. Nearly every city in this table has a meaningful 750 sq ft cliff. Shrink the ADU to 749 sq ft and several cities drop $5,000–$11,000 in impact fees alone. The cheapest ADU in California isn’t in the cheapest city; it’s the 749 sq ft ADU in a high-cliff city.
How to use this table
- Find your city (or nearest published neighbor) for a planning baseline.
- Read that city’s full post — the total is the headline; the ledger is the tool.
- Check the cliff before finalizing square footage. The 750 line is worth more than any city choice.
- Verify the asterisked items with the city. Our totals are honest about what’s confirmed and what isn’t.
Full city posts
- Long Beach ADU Cost 2026
- Torrance ADU Cost 2026
- Anaheim ADU Cost 2026
- Oakland ADU Cost 2026
- San Francisco ADU Cost 2026
- Riverside ADU Cost 2026
- Fontana ADU Cost 2026
- Salinas ADU Cost 2026
- Lakewood ADU Cost 2026
- Oceanside ADU Cost 2026
- Chula Vista ADU Cost 2026
- San Bernardino ADU Cost 2026
- Pasadena ADU Cost 2026
- Campbell ADU Cost 2026
- Palo Alto ADU Cost 2026
- San Diego ADU Cost 2026
- Santa Maria ADU Cost 2026
- Sacramento ADU Cost 2026
- Fullerton ADU Cost 2026
- Burbank ADU Cost 2026
Coming next
Downey, Oxnard, Santa Ana, and Lancaster publish with firm or near-firm totals — all four sit in the $305,000–$311,000 band and will fill the middle of this table. The December update re-ranks everything, and the SB 1117 cliff change takes effect January 1, 2027 — watch the cliff lines, not just the totals.