Published: 8 Nov 2026 · Last verified: 27 Oct 2026 · Next review: Jan 2027 Cost figures are re-checked against permit records quarterly. Changes are logged in Corrections.
Unincorporated San Mateo County’s $314,637 floor is the only ledger in this series built from a full county permit stack — $8,333 in flat county fees computed line by line from the county’s own schedules, not a single fee line. It also has the series’ most honest complication: the school fee depends on the parcel’s district, and the surcharges are quantified but deliberately uncounted.
The permit stack is the core of the post. The Building Service Fee Schedule (effective April 1, 2026) charges new residential construction at $8.33 per square foot, covering permit processing, plan review, and inspection — $6,664 on 800 sq ft. The Full Review application filing fee adds $595. The Planning Service Fee Schedule (effective July 23, 2026) charges $887 for Planning Review of Building Permit Plans including one resubmittal. The county fire review adds $187 for single-family new construction under Note 7. That is $8,333 in flat county fees before the school line.
The school line is $4,304, but it must be read with its qualifier: it is the Menlo Park City School District plus Sequoia Union High School District combined rate at the $5.38 statutory limit, adopted by MPCSD Resolution 25.26.15 (April 16, 2026, effective June 15, 2026) with a 40% / 60% high-school / feeder split. Unincorporated county parcels fall in many districts; a North Fair Oaks parcel, for example, is in different districts entirely. The $4,304 is counted because it is a verified 2026 adoption for a real subset of county parcels — and the draft says so, rather than pretending it is countywide.
Two confirmed zeros anchor the stack: the Affordable Housing Impact Fee exempts second units on the county’s own fees page, and the Zoning Ordinance (§8.392.050(16)) provides ADUs shall not be subject to design review — both $0, not missing.
The short answer
| 800 sq ft detached ADU · San Mateo County (unincorporated) · 2026 | Amount |
|---|---|
| Total build cost (floor — see exclusions) | $314,637 |
| Cost per square foot | $393 |
| Largest single line | Systems + interior, $147,000 |
| Building permit (residential, $8.33/sq ft) | $6,664 |
| Application filing fee (Full Review) | $595 |
| Planning review of building permit plans | $887 |
| Fire review (single family, new construction) | $187 |
| School district fee (MPCSD + Sequoia Union) | $4,304 |
| Affordable Housing Impact Fee | $0 — second units exempt |
| Design review | $0 — ADUs exempt by ordinance |
| Percentage surcharges | Not counted — $1,621.96 quantified, see autopsy |
| Sewer / water connection | Not counted — special districts |
| Pre-approved plans | None located — verify with county |
| 750 sq ft cliff | State law only — AHIF exempt; roadway mitigation unconfirmed |
The full line-item breakdown
Six phases. The same six used on every build in this series.
| Phase | Cost | Share |
|---|---|---|
| Soft costs (design, permits, fees) | $26,637 | 9% |
| Site work + foundation | $38,000 | 12% |
| Framing + structure | $48,000 | 15% |
| Building envelope | $42,000 | 13% |
| Systems + interior | $147,000 | 47% |
| Landscaping & hardscape | $13,000 | 4% |
| Total | $314,637 | $393 / sq ft |
The county’s fee lines are also listed on the San Mateo County fee page, with verification status and source links.
The fee autopsy
Every fee line we found, with exactly what it is and where it came from.
| Fee line | Amount | Source / status |
|---|---|---|
| Design & engineering | $14,000 | Series baseline, carried |
| Building permit, residential new construction | $6,664 | Building Service Fee Schedule eff. 4/1/2026: $8.33/sq ft × 800, covers permit processing, plan review, inspection |
| Application filing fee, Full Review | $595 | Building Service Fee Schedule: new residential structures; non-refundable, in addition to schedule fees (Note 1) |
| Planning review of building permit plans | $887 | Planning Service Fee Schedule eff. 7/23/2026: plan review + 1 resubmittal |
| Fire review, single family | $187 | Planning Service Fee Schedule, Note 7: fire review applies to new construction; single-family rate |
| School fee, MPCSD + Sequoia Union | $4,304 | MPCSD Resolution 25.26.15 (adopted 4/16/2026, eff. 6/15/2026): $5.38 limit, 40% HS / 60% feeder — Menlo Park-area parcels; other areas differ by district |
| Affordable Housing Impact Fee | $0 | County fees page: exemptions include second units |
| Design review | $0 | Zoning Ordinance Ch. 8.392 §8.392.050(16): ADUs shall not be subject to design review |
| Technology / document storage / legal surcharges | Not counted — $896.06 quantified | 4% / 2% / 5% on the $8,146 planning-plus-building stack; excluded pending combined-fee worksheet confirmation |
| Planning administration | Not counted — $725.90 quantified | 10% of the $7,259 building stack (Note 4: applies to new residential permits); excluded with the surcharges above |
| Geotechnical report review | Not counted — $892 building / $773 planning | Conditional: applies only where a geotechnical report is required (fault, landslide, liquefaction, coastal-bluff, Seal Cove, grading, subdivision triggers) |
| Public Works review | Not counted — $400 | Other-agency review fee; trigger for an ADU unclear |
| Roadway mitigation fees | Not counted | Ordinance 3277, square-footage based — rate not located |
| Mid-Coast park fees | Not counted | Ordinance 4155, Mid-Coast area only (Montara, Moss Beach, El Granada, Miramar, Princeton) |
| Sewer / water connection + capacity | Not counted | Served by special districts — verify with provider |
The ADU law box
Three state rules frame every number above. Under Government Code §65852.2(f)(3)(A), a local agency may not impose impact fees on an ADU under 750 square feet; at 750 or above, fees are charged proportionately to the primary dwelling’s size. Under §66311.5 (SB 1117, effective January 1, 2027), per-square-foot impact fees on two or fewer ADUs are charged only on the area above 750 square feet — 50 square feet on this 800 sq ft benchmark — and connection and capacity charges are excluded from that rule. School fees are a separate statute: under SB 543, ADUs under 500 square feet pay $0 in school fees, and at 800 square feet the full district rate applies. SB 1117 does not reduce school fees, and it does not change any line counted in this post: the Affordable Housing Impact Fee is already $0 for second units, no per-square-foot impact fee is counted, and the school fee is untouched by SB 1117.
Three things that can still move the number
- The surcharges. $1,621.96 is quantified from the schedules but excluded on a base question. Confirming the county’s combined-fee worksheet at permit time would move the floor to about $316,259 — the single largest known adjustment.
- The parcel’s school district. The counted $4,304 is the Menlo Park-area pair. Parcels in other districts pay those districts’ rates, which may be lower or at the same $5.38 limit. District determination is mandatory before budgeting this line.
- Location-specific fees. A Mid-Coast parcel owes park fees; a parcel needing a geotechnical report owes $892 and possibly $773 more; roadway mitigation applies countywide at an unlocated rate. Any of these can add four figures to a specific parcel’s total.
How San Mateo County compares
Only published posts are used here. Published Bay Area totals: Palo Alto ~$313,000, Campbell ~$310,000, Oakland $322,000. The county’s $314,637 sits mid-band — and unlike the city floors around it, it already counts a full permit stack. Add the $1,621.96 in surcharges and it reaches about $316,259, still mid-band, before any parcel-specific fees. That completeness is the point: this floor is closer to a budget than the thinner city floors around it.
A note on SB 1117
Signed September 2026, effective January 2027: for a homeowner’s first two ADUs, impact fees may apply only to square footage above 750, calculated marginally. San Mateo County’s Affordable Housing Impact Fee is already $0 for second units, and no per-square-foot impact fee is counted in this ledger, so SB 1117 changes nothing we can compute here — there is nothing to reduce. See the full comparison at San Mateo County: 2026 vs 2027, line by line. School fees, permit fees and sewer/water charges are outside SB 1117’s impact-fee definition and do not change.
What this post does not claim
It does not claim the school fee is $4,304 for every unincorporated parcel — it is the Menlo Park-area pair, and other districts differ. It does not claim surcharges are $0 — it claims $1,621.96 is quantified but excluded on a worksheet question. It does not claim sewer and water cost $0 — they are served by special districts and entirely uncounted. Construction phases 2–6 are the series baseline, not county bids.
Sources
- County of San Mateo, Building Service Fee Schedule (established by Resolution 080751, adopted November 19, 2024; effective April 1, 2026) — residential new construction $8.33/sq ft; Full Review filing $595; geotechnical ADU review $892; Planning Administration 10% of building fees (Note 4). https://www.smcgov.org/media/157829/download?inline= (as of 27 Oct 2026)
- County of San Mateo, Planning Service Fee Schedule (established by Resolution 080751; amended by Resolution 082009, adopted June 23, 2026; effective July 23, 2026) — Planning Review of Building Permit Plans $887; fire review single family $187 (Note 7); technology 4%, document storage 2%, legal counsel 5%; Public Works review $400. https://www.smcgov.org/media/160187/download?inline= (as of 27 Oct 2026)
- Menlo Park City School District, Resolution No. 25.26.15 — adoption of the 2026 fee justification study and increase to the $5.38 SAB limit, shared with Sequoia Union HSD (40% / 60%). http://district-mpcsd.community.highbond.com/document/448cebae-1078-4430-8fcc-70b7688016ce/ (as of 27 Oct 2026)
- County of San Mateo, Affordable Housing Impact Fee page — exemptions include second units. https://www.smcgov.org/planning/affordable-housing-impact-fee-0 (as of 27 Oct 2026)