Published: 17 Nov 2026 · Last verified: 13 Nov 2026 · Next review: Jan 2027 Cost figures are re-checked against permit records quarterly. Changes are logged in Corrections.
The same 800 sq ft detached ADU. Sixteen cities. A building permit that costs $1,006 in one and $19,200 in another — a 19x spread for the identical stack of paper.
This is the purest ranking this site has published: one line item, every city, no construction costs, no impact fees, no school districts. Just the price of permission.
The ranking
Every figure below is taken from that city’s published post (keyFacts), for an 800 sq ft detached ADU. The asterisk (*) is doing real work: it marks any figure that is partial, estimated, modeled from a valuation schedule, or priced from older rate tables — exactly as each city’s post states. Unasterisked figures come straight from a published fee schedule.
| Rank | City | Building permit + plan check (800 sq ft) | Pricing model |
|---|---|---|---|
| 1 | Riverside | $1,006 | Series low — flat schedule |
| 2 | Torrance | $1,006–$1,672* | Valuation-based range |
| 3 | Anaheim | $1,672* | Valuation schedule, modeled |
| 4 | Fullerton | ~$2,532* | Valuation schedule, estimated |
| 5 | Fontana | $3,195 | Published schedule |
| 6 | Long Beach | ≈ $3,200 | Published schedule |
| 7 | Burbank | $3,692* | Valuation + plan check, modeled |
| 8 | Campbell | ~$3,929* | Valuation schedule, estimated |
| 9 | Chula Vista | $3,951 | Flat — no valuation math |
| 10 | Garden Grove | ~$5,176* | Valuation schedule, estimated |
| 11 | Oceanside | $5,378 | Sq-ft-based; FY 2026-27 schedule |
| 12 | Palo Alto | ~$5,790* | 1.76% of valuation, estimated |
| 13 | Salinas | ~$6,226 | Published schedule |
| 14 | Pasadena | $7,000–$13,000* | Valuation-based range |
| 15 | Glendale | ≈ $8,550* | Valuation schedule, estimated |
| 16 | Oakland | $12,800–$19,200 | 4–6% of valuation |
Four pricing philosophies run the table. Flat schedules (Riverside, Chula Vista) tell you the number before you file. Valuation-based fees (the majority, and all three of the most expensive) multiply an assumed construction value by a tiered rate — which is why the top of this ranking belongs to the cities that assume the most expensive builds. Square-footage-based (Oceanside) prices the drawings by size. And Oakland’s 4–6% is valuation-based with the steepest rate in the series — no asterisk, because the rate is published; only the assumed valuation moves the range.
Five things the ranking shows
1. The pricing model matters more than the city. The three cheapest permits include two flat schedules; the five most expensive are all valuation-based. A city does not need high fees to land at the top — it needs a valuation schedule that assumes an expensive build and a high percentage. Oakland’s 4–6% is the extreme: on a $320,000 assumed valuation, 6% is $19,200 before a single impact fee is charged.
2. Most of this table is asterisked — and that is the point. Nine of sixteen figures carry a *. The asterisk is not a shrug; it is the site’s honesty mechanism. Oceanside’s $5,378 carries none: it is plan check $1,862.70 + inspection $3,515.40 straight from the city’s FY 2026-27 fee schedule, with the detached ADU confirmed as new single-family construction — the old ~$7,541 figure, built from 2018 and 2021 tables with fire and water review added, is retired. (Twelve percent in surcharges still applies at Oceanside’s counter, on top of the $5,378.) Anaheim’s $1,672 and Burbank’s $3,692 are modeled from valuation schedules the cities publish but do not pre-compute for ADUs. Each city’s post documents exactly what its asterisk means. Read the asterisk before you read the number.
3. Riverside owns the bottom — twice. $1,006 is the series low (Fullerton’s $1,223 held the record before Riverside’s research), and Torrance merely ties its starting point. Riverside pairs the cheap permit with an 800 sq ft free pre-approved plan — the first city whose free plan matches our standard post size exactly, meaning both the design line and the permit line shrink at once.
4. The flat-fee experiment is winning on transparency. Chula Vista’s $3,951 is mid-table on price but first on knowability: $476 intake + $533 plan check + $2,942 inspection, printed in one line of Fee Bulletin 10-400, no valuation math, no asterisk. Compare that with Glendale’s ≈$8,550* — nearly 2.2x the price, and an estimate. Transparency is not the same as cheapness, but it is the only one of the two a homeowner can bank on at the counter.
5. Oakland’s top is honest — and structural. Oakland exempts ADUs from impact fees entirely (two city documents say so), so the permit carries what other cities spread across impact-fee lines: $12,800–$19,200 at 4–6% of valuation, plus the $4,136 school fee. The ranking’s most expensive permit belongs to one of its most ADU-friendly fee philosophies. That is not a contradiction; it is the tradeoff, stated plainly.
A correction we owe you
The content calendar for this post listed the range as $1,006 to $7,541 — the top being Oceanside’s partial figure. That was wrong, or at least incomplete: the verified data runs to Oakland’s $12,800–$19,200, which this site has published since the Oakland research. The title and description above carry the honest range, and this paragraph stays attached to the post so the correction is part of the record. This site’s core value is honesty; that includes about our own calendar.
Cities not ranked
Ranked above are the sixteen cities whose posts carry a permitFee keyFacts value. Excluded, with reasons:
- No keyFacts field (older posts): San Diego, San Francisco, San Jose, Sacramento, Santa Maria — these posts predate the Key Facts feature, so their permit figures live in the post bodies, not in a comparable frontmatter field. (For reference: the San Diego post publishes ~$16,500 for City of San Diego plan check + inspection; the Bay Area comparison publishes ~$19,500 for San Francisco and $5,103 for San Jose. A future edition will fold these in once their posts carry keyFacts.)
- Not a number: Lakewood (“County schedule*”) and San Bernardino (“Verify with city”) — and Lancaster, whose building permit valuation table is not in the city’s public index (post published 15 Nov 2026; school and impact fees confirmed, permit unpublished).
- No post yet: Santa Ana is researched in our fee matrix but its full post is not yet published (18 Nov 2026).
What changes January 1, 2027
Nothing in this table. SB 1117 narrows impact fees to square footage above 750 for a homeowner’s first two ADUs; building permit fees, plan check fees, and taxes are not impact fees under the statute and are unaffected. Riverside’s $1,006 and Oakland’s $12,800–$19,200 are the same numbers on January 2 as they are today. The 48-day countdown covers what the new law does move.
Disclaimer
Model estimates, not quotes. Asterisked figures are partial, estimated, or assumption-based as documented in each city’s post — read the asterisk’s footnote before budgeting. Fee schedules change annually. Always verify current fees with your city’s building department before budgeting.